105 Flood Av
San Francisco permit 202111303348 · West of Twin Peaks
Convert existing detached garage into a new adu.
- Filed
- Nov 30, 2021
- Issued
- Dec 21, 2022 (13 months after filing)
- Completed
- Sep 10, 2024 (21 months after issuance)
- Review stops
- 23 stops across 5 departments
- Comments issued
- None
- Put on hold
- 9 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Planning review Planning · CP-GEN | Nov 30, 2021 | Dec 8, 2021 | — |
Zoning review Planning · CP-ZOC | Dec 8, 2021 | Oct 24, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 8, 2021 | Sep 19, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Dec 8, 2021 | Oct 26, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 8, 2021 | Jan 12, 2022 | — |
Fire prevention review Fire Department · SFFD | Dec 8, 2021 | Dec 8, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Dec 8, 2021 | Aug 1, 2022 | — |
Urban forestry Public Works · DPW-BUF | Dec 8, 2021 | Oct 5, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 8, 2021 | Jan 31, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 29, 2022 | Jul 29, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 29, 2022 | Aug 2, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jul 29, 2022 | Dec 20, 2022 | — |
Planning review Planning · CP-GEN | Aug 15, 2022 | Aug 15, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 16, 2022 | Sep 19, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Sep 16, 2022 | Sep 19, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 16, 2022 | Sep 20, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 21, 2022 | Oct 21, 2022 | — |
Building plan review Building Inspection · BLDG | Oct 24, 2022 | Oct 26, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 24, 2022 | Oct 24, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Oct 24, 2022 | Oct 27, 2022 | — |
Urban forestry Public Works · DPW-BUF | Oct 24, 2022 | Oct 31, 2022 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Oct 24, 2022 | Oct 25, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 20, 2022 | Dec 21, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $54,000
| Name | Role | License on permit |
|---|---|---|
| Choi-Keung Chau | Architect | C73652 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025