1950 Page St
San Francisco permit 202111303356 · Haight Ashbury
Vertical addition to convert/legalize (e)boys/girls club to performing art school w/6 teacher housing units. build out 2/f at front bldg. add 3/f, setback 35' from rear prop. line. remove (e) indoor pool. raise flr level & add 7 space garage w/ 133 bicycle parking. total 25 classrms, 6 dance studios
- Filed
- Nov 30, 2021
- Issued
- Sep 19, 2024 (34 months after filing)
- Completed
- Not completed yet
- Review stops
- 63 stops across 7 departments
- Comments issued
- 16 times, by Building Inspection, Fire Department, Public Health, Public Works
- Put on hold
- 4 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 30, 2021 | Jan 5, 2022 | Administrative |
Zoning review Planning · CP-ZOC | Jan 5, 2022 | Feb 22, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jan 5, 2022 | Jun 27, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Feb 22, 2022 | Feb 27, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Feb 23, 2022 | Mar 24, 2022 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 23, 2022 | Nov 8, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 23, 2022 | Apr 20, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 23, 2022 | Mar 29, 2022 | — |
Public health review Public Health · HEALTH | Feb 23, 2022 | Mar 28, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 24, 2023 | Nov 8, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 24, 2023 | Mar 5, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 24, 2023 | Nov 10, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Oct 24, 2023 | Oct 25, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Nov 8, 2023 | Nov 8, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 10, 2023 | Nov 10, 2023 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Mar 4, 2024 | Mar 21, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Mar 4, 2024 | Mar 5, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 4, 2024 | Mar 19, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Mar 4, 2024 | Mar 6, 2024 | Approved |
Public health review Public Health · HEALTH | Mar 4, 2024 | Mar 5, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 6, 2024 | Mar 6, 2024 | Issued Comments |
Public health review Public Health · HEALTH | Mar 14, 2024 | Mar 14, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 27, 2024 | Mar 28, 2024 | Approved |
Zoning review Planning · CP-ZOC | Mar 27, 2024 | Mar 28, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 27, 2024 | Apr 1, 2024 | Approved-Stipulated |
Public health review Public Health · HEALTH | Mar 27, 2024 | Mar 28, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 27, 2024 | Apr 2, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Mar 28, 2024 | Mar 28, 2024 | Issued Comments |
Public health review Public Health · HEALTH | Apr 22, 2024 | Apr 22, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 31, 2024 | Jun 5, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | May 31, 2024 | May 31, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 31, 2024 | Jun 4, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 31, 2024 | Jun 4, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | May 31, 2024 | Jun 4, 2024 | Approved |
Public health review Public Health · HEALTH | May 31, 2024 | Jun 3, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jun 6, 2024 | Jun 7, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Jun 6, 2024 | Jun 6, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 6, 2024 | Jun 7, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 6, 2024 | Jun 10, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jun 6, 2024 | Jun 7, 2024 | Approved |
Public health review Public Health · HEALTH | Jun 6, 2024 | Jun 17, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 11, 2024 | Jun 14, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jun 11, 2024 | Jun 11, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 11, 2024 | Jun 12, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jun 11, 2024 | Jun 13, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jun 14, 2024 | Jun 14, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 14, 2024 | Jun 14, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 14, 2024 | Jun 26, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jun 14, 2024 | Jun 20, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jun 17, 2024 | Jun 17, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Jun 27, 2024 | Jun 27, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jun 27, 2024 | Sep 19, 2024 | Administrative |
Addendum 2: Excavation/grading/foundation
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 3, 2025 | Jan 23, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 28, 2025 | Mar 21, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Mar 21, 2025 | Apr 11, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 21, 2025 | Mar 24, 2025 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Mar 21, 2025 | Apr 10, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 21, 2025 | In progress | In Progress |
Building plan review Building Inspection · BLDG | Aug 7, 2025 | Aug 27, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 7, 2025 | Aug 8, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 4, 2026 | Mar 16, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 23, 2026 | Oct 27, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $16,695,000
| Name | Role | License on permit |
|---|---|---|
| Yang Nie Nie Yang Architects | Architect | C31413 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025