1645 V Jones St
San Francisco permit 202112013377 · Nob Hill
To construct a new 2 unit residential of type v-b, 4-story over 1 basement
- Filed
- Dec 1, 2021
- Issued
- Oct 29, 2025 (47 months after filing)
- Completed
- Not completed yet
- Review stops
- 71 stops across 6 departments
- Comments issued
- 26 times, by Planning, Building Inspection, Fire Department, Public Works, Public Utilities, Permit Center
- Put on hold
- Twice
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 1, 2021 | Dec 1, 2021 | — |
Zoning review Planning · CP-ZOC | Dec 1, 2021 | Oct 16, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Dec 1, 2021 | Oct 2, 2025 | Administrative |
Planning neighborhood notice Planning · CP-NP | May 24, 2023 | Jun 1, 2023 | — |
Zoning review Planning · CP-ZOC | Oct 16, 2023 | Oct 16, 2023 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Oct 16, 2023 | Oct 16, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 16, 2023 | Oct 30, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 16, 2023 | Nov 17, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 16, 2023 | Nov 28, 2023 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Oct 16, 2023 | Nov 14, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 16, 2023 | Nov 1, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Oct 16, 2023 | Oct 26, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 10, 2024 | Dec 26, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 10, 2024 | Dec 26, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 18, 2024 | Dec 18, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Dec 24, 2024 | Feb 11, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 24, 2024 | Jan 7, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Dec 24, 2024 | Dec 24, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 24, 2024 | Dec 31, 2024 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Feb 26, 2025 | Apr 2, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | May 15, 2025 | May 28, 2025 | Approved |
Fire prevention review Fire Department · SFFD | May 27, 2025 | May 27, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 27, 2025 | May 30, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 2, 2025 | Jun 2, 2025 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Jun 3, 2025 | Jun 3, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 13, 2025 | Jul 11, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 13, 2025 | Jun 13, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 23, 2025 | Jun 23, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jul 17, 2025 | Jul 17, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Jul 31, 2025 | Jul 31, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 25, 2025 | Sep 25, 2025 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Sep 25, 2025 | Sep 25, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 25, 2025 | Sep 29, 2025 | Approved |
Development fee collection Building Inspection · DFCU | Sep 29, 2025 | Sep 29, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 2, 2025 | Oct 29, 2025 | Administrative |
Addendum 1: Final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 20, 2025 | Dec 15, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Feb 12, 2026 | Mar 5, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 16, 2026 | Mar 16, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Mar 16, 2026 | Mar 19, 2026 | Approved |
Building plan review Building Inspection · BLDG | Mar 16, 2026 | May 6, 2026 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Mar 16, 2026 | May 5, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 16, 2026 | Apr 3, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 16, 2026 | Mar 21, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Mar 16, 2026 | Apr 1, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Mar 16, 2026 | May 4, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 16, 2026 | Mar 19, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Mar 16, 2026 | Apr 3, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 16, 2026 | In progress | — |
Building plan review Building Inspection · BLDG | May 6, 2026 | May 29, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Jun 26, 2026 | Jun 29, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 26, 2026 | Jul 14, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 26, 2026 | Jul 23, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 26, 2026 | Jun 30, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 26, 2026 | Jun 29, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Jun 26, 2026 | Jul 6, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jun 26, 2026 | Jul 19, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 26, 2026 | Jun 29, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Jun 26, 2026 | Jul 2, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 30, 2026 | Jun 30, 2026 | Approved |
Zoning review Planning · CP-ZOC | Sep 14, 2026 | Sep 15, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 14, 2026 | Sep 21, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 14, 2026 | Sep 28, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 14, 2026 | Sep 22, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Sep 14, 2026 | Sep 16, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Sep 14, 2026 | Sep 17, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 14, 2026 | Sep 23, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 14, 2026 | Sep 22, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Sep 14, 2026 | Sep 18, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Issued
- Estimated cost
- $1,316,193
| Name | Role | License on permit |
|---|---|---|
| Francisco J Matos Architects Sf | Architect | C34078 |
| Jonathan Carroll Bradley Eag Studio | Architect | C-38856 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025