22 Fountain St
San Francisco permit 202112073932 · Noe Valley
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Remodel (e) in conjunction w/ pa 201712085886 & 201712085881 including all (n) foundations, plumbing, electrical, mech, windows, etc. (n) adu at ground flr.
- Filed
- Dec 7, 2021
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 11 stops across 4 departments
- Comments issued
- Once, by Building Inspection
- Put on hold
- 3 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 20, 2021 | Dec 20, 2021 | — |
Zoning review Planning · CP-ZOC | Dec 20, 2021 | May 22, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Feb 9, 2023 | Feb 9, 2023 | — |
Permit Processing Center Building Inspection · PPC | Feb 9, 2023 | In progress | — |
Building plan review Building Inspection · BLDG | May 22, 2023 | May 3, 2024 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | May 22, 2023 | In progress | In Progress |
Street use and mapping Public Works · DPW-BSM | May 22, 2023 | Jun 21, 2023 | — |
Building pre-screening Building Inspection · PRE-BLDG | May 23, 2023 | May 23, 2023 | — |
Building plan review Building Inspection · BLDG | May 3, 2024 | May 28, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $500,000
| Name | Role | License on permit |
|---|---|---|
| Earle Edward Weiss E E Weiss Architect | Architect | C22416 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Oct 2015