600 Wisconsin St
San Francisco permit 202112083976 · Potrero Hill
Renov per plans, add 1,021 sq. ft. 3/f, unconditioned decks, office/ bedrm w/closet, bathrm, (n) stucco finish parapet/roof @ 3/f add, raise ceiling height l2, replace/reconfig ext envelope/stucco/wd siding, modification to (e) bay window to accommodate (n) 3/f addition
- Filed
- Dec 8, 2021
- Issued
- Aug 23, 2023 (20 months after filing)
- Completed
- Sep 1, 2026 (36 months after issuance)
- Review stops
- 15 stops across 5 departments
- Comments issued
- None
- Put on hold
- 3 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 8, 2021 | Dec 14, 2021 | — |
Zoning review Planning · CP-ZOC | Dec 14, 2021 | Oct 18, 2022 | — |
Planning neighborhood notice Planning · CP-NP | Jul 19, 2022 | Jul 22, 2022 | — |
Permit Center Permit Center · PERMIT-CTR | Sep 30, 2022 | Sep 30, 2022 | — |
Building plan review Building Inspection · BLDG | Oct 19, 2022 | Feb 9, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 10, 2023 | Aug 4, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 13, 2023 | Apr 3, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Apr 3, 2023 | Jul 26, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 4, 2023 | Aug 4, 2023 | Approved |
Building plan review Building Inspection · BLDG | Aug 4, 2023 | Aug 7, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 8, 2023 | Aug 9, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 10, 2023 | Aug 11, 2023 | Approved |
Zoning review Planning · CP-ZOC | Aug 14, 2023 | Aug 16, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 17, 2023 | Aug 17, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 17, 2023 | Aug 23, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $700,000
| Name | Role | License on permit |
|---|---|---|
| P Casper Mork-Ulnes Mork-Ulnes Architects | Architect | C33031 |
| David M Strandberg Strandberg Engineering | Engineer | 62993 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025