216 Eddy St
San Francisco permit 202112084018 · Tenderloin
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revisions to pa #202008061226 & 202109077832: changes to the trash/laundry rooms/elevator vestibule layout in basement & service offices on the g/f. wheel chair lift omitted as no longer needed; inclusion of stair shop drawings for stair 00 previously deferred; g/f (e) steel beams along
- Filed
- Dec 8, 2021
- Issued
- Apr 12, 2022 (4 months after filing)
- Completed
- Dec 28, 2022 (9 months after issuance)
- Review stops
- 17 stops across 3 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 4 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 8, 2021 | Mar 15, 2022 | — |
Fire prevention review Fire Department · SFFD | Dec 8, 2021 | Dec 8, 2021 | — |
Central Permit Bureau Building Inspection · CPB | Jan 10, 2022 | Jan 10, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jan 10, 2022 | Apr 11, 2022 | — |
Building plan review Building Inspection · BLDG | Jan 11, 2022 | Jan 25, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 25, 2022 | Mar 8, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Jan 25, 2022 | Mar 29, 2022 | — |
Disability access review Mayor's Office on Disability · MOD | Jan 26, 2022 | Mar 24, 2022 | — |
Building plan review Building Inspection · BLDG | Mar 15, 2022 | Mar 16, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 15, 2022 | Mar 22, 2022 | — |
Fire prevention review Fire Department · SFFD | Mar 15, 2022 | Mar 30, 2022 | — |
Building plan review Building Inspection · BLDG | Mar 30, 2022 | Apr 1, 2022 | — |
Disability access review Mayor's Office on Disability · MOD | Mar 30, 2022 | Apr 5, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 30, 2022 | Mar 30, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Mar 30, 2022 | Apr 4, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Apr 11, 2022 | Apr 12, 2022 | — |
Apartment and hotel inspection Building Inspection · HIS | Apr 12, 2022 | Apr 12, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Christopher Alexandre Duncan Gelfand Partners | Architect | C23282 |
| Edward Charles Robison Edward C. Robinson, Pe | Engineer | C65883 |
| Marc Andrew Steyer Tipping Structural Engineers | Engineer | S6022 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026