38 Granada Av
San Francisco permit 202112144411 · Oceanview/Merced/Ingleside
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Altered site to bpa# 2019-0917-1815-s: remove vertical addition from approved scope of work, retain horizontial addition and interior remodel per plans.
- Filed
- Dec 14, 2021
- Issued
- Mar 7, 2022 (3 months after filing)
- Completed
- Nov 6, 2023 (20 months after issuance)
- Review stops
- 15 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 6 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 14, 2021 | Dec 16, 2021 | — |
Zoning review Planning · CP-ZOC | Dec 16, 2021 | Dec 20, 2021 | — |
Building plan review Building Inspection · BLDG | Dec 21, 2021 | Feb 24, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jan 10, 2022 | Feb 25, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 13, 2022 | Feb 9, 2022 | — |
Permit Processing Center Building Inspection · PPC | Mar 1, 2022 | Mar 1, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Mar 1, 2022 | Mar 7, 2022 | — |
Addendum 1: Foundation/mechanical/power
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 17, 2022 | Mar 17, 2022 | — |
Building plan review Building Inspection · BLDG | Mar 18, 2022 | Jun 3, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 22, 2022 | May 16, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 16, 2022 | May 17, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 6, 2022 | Jun 6, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 6, 2022 | Jun 9, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jun 13, 2022 | Jun 14, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jun 14, 2022 | Jun 16, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| James Carlos Welch Romano Welch Architects | Architect | C32474 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022