697 Rhode Island St
San Francisco permit 202112154459 · Potrero Hill
Renovation of existing(2)bed(1)bath unit to a(2)bed(1.5)bath unit (unit #2) renovation is of the unit at the rear of the site which is on both the 1st floor&basement level. it is not related to adu or legalization
- Filed
- Dec 15, 2021
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 41 stops across 5 departments
- Comments issued
- 19 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 29, 2021 | Dec 29, 2021 | — |
Zoning review Planning · CP-ZOC | Dec 29, 2021 | Apr 23, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 24, 2024 | May 21, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 20, 2024 | May 20, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | May 20, 2024 | May 20, 2024 | Not Applicable |
Structural plan approval Building Inspection · PAD-STR | Sep 6, 2024 | Oct 16, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 21, 2024 | Oct 23, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 2, 2024 | Dec 2, 2024 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Jul 11, 2025 | Jul 17, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jul 17, 2025 | Jun 23, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jul 17, 2025 | Aug 11, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 17, 2025 | Aug 5, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jul 17, 2025 | Jul 30, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 17, 2025 | Jul 18, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 17, 2025 | Jul 23, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jul 17, 2025 | Aug 13, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 17, 2025 | Jul 25, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 17, 2025 | Jul 24, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Nov 10, 2025 | Dec 1, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 17, 2025 | Nov 17, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Nov 19, 2025 | Nov 19, 2025 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Nov 21, 2025 | Dec 1, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 24, 2025 | Nov 24, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 2, 2025 | Dec 2, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 29, 2026 | May 14, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 30, 2026 | May 6, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 30, 2026 | May 6, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 4, 2026 | May 4, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 8, 2026 | May 15, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 14, 2026 | May 14, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 3, 2026 | Jun 12, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jun 5, 2026 | Jun 5, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 8, 2026 | Jun 15, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jun 12, 2026 | Jun 12, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 12, 2026 | Jun 12, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 8, 2026 | Jul 13, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 9, 2026 | Jul 9, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 10, 2026 | Jul 13, 2026 | Approved |
Development fee collection Building Inspection · DFCU | Jul 13, 2026 | Jul 22, 2026 | Administrative |
Zoning review Planning · CP-ZOC | Jul 22, 2026 | Jul 22, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 24, 2026 | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $295,000
| Name | Role | License on permit |
|---|---|---|
| Robert Gerson Siol Inc | Architect | C-33297 |
| Hao-Yun Mei | Architect | C38279 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025