55 Cyril Magnin St
San Francisco permit 202112224938 · Tenderloin
Barrier removal related to the accessible business entrance program, cat ii. inclusive of work at the accessible van parking (porte-cochere), regrading at cyril magnin sidewalk & (e) accessible platform lift.
- Filed
- Dec 22, 2021
- Issued
- May 17, 2024 (29 months after filing)
- Completed
- Aug 28, 2024 (3 months after issuance)
- Review stops
- 12 stops across 6 departments
- Comments issued
- None
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Dec 22, 2021 | Dec 22, 2021 | — |
Zoning review Planning · CP-ZOC | Dec 22, 2021 | Dec 22, 2021 | Approved |
Building plan review Building Inspection · BLDG | Jan 21, 2022 | Jan 21, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Jan 21, 2022 | Jan 21, 2022 | — |
Fire prevention review Fire Department · SFFD | Jan 21, 2022 | Jan 21, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jan 21, 2022 | Oct 5, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 21, 2022 | Jan 21, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 20, 2023 | Dec 20, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Dec 20, 2023 | Dec 20, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 20, 2023 | Dec 20, 2023 | Approved |
Public health review Public Health · HEALTH | Dec 20, 2023 | Dec 20, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | May 17, 2024 | May 17, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $600,000
| Name | Role | License on permit |
|---|---|---|
| Daniel G Lewin Mccall Design Group | Engineer | C38406 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2020