4043 19th St
San Francisco permit 202112285077 · Castro/Upper Market
Excavate under bldg for new basement & garage. add 10'-0" curb cut at new garage entry. reconstruct front stair. renovate interior. add residential elevator.
- Filed
- Dec 28, 2021
- Issued
- Apr 14, 2023 (16 months after filing)
- Completed
- Oct 17, 2024 (18 months after issuance)
- Review stops
- 32 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 6 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 28, 2021 | Jan 11, 2022 | — |
Zoning review Planning · CP-ZOC | Jan 11, 2022 | Aug 29, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jan 11, 2022 | Apr 7, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Jul 7, 2022 | Jul 8, 2022 | — |
Building plan review Building Inspection · BLDG | Aug 30, 2022 | Mar 3, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 30, 2022 | Jan 10, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 30, 2022 | Sep 13, 2022 | — |
Fire prevention review Fire Department · SFFD | Aug 30, 2022 | Aug 31, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Aug 30, 2022 | Mar 30, 2023 | — |
Zoning review Planning · CP-ZOC | Oct 5, 2022 | Oct 24, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 5, 2022 | Oct 11, 2022 | — |
Fire prevention review Fire Department · SFFD | Oct 5, 2022 | Oct 6, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 27, 2022 | Jan 25, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 27, 2022 | Dec 29, 2022 | — |
Fire prevention review Fire Department · SFFD | Dec 27, 2022 | Jan 9, 2023 | — |
Zoning review Planning · CP-ZOC | Feb 22, 2023 | Mar 13, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 22, 2023 | Feb 27, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 22, 2023 | Feb 24, 2023 | — |
Fire prevention review Fire Department · SFFD | Feb 22, 2023 | Mar 2, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 3, 2023 | Mar 16, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 6, 2023 | Mar 15, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 6, 2023 | Mar 8, 2023 | — |
Fire prevention review Fire Department · SFFD | Mar 6, 2023 | Mar 9, 2023 | — |
Fire prevention review Fire Department · SFFD | Mar 10, 2023 | Mar 10, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 10, 2023 | Mar 10, 2023 | — |
Zoning review Planning · CP-ZOC | Apr 3, 2023 | Apr 5, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 3, 2023 | Apr 6, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 3, 2023 | Apr 5, 2023 | — |
Fire prevention review Fire Department · SFFD | Apr 3, 2023 | Apr 7, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Apr 3, 2023 | Apr 5, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 3, 2023 | Apr 4, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Apr 7, 2023 | Apr 14, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $850,000
| Name | Role | License on permit |
|---|---|---|
| Jonathan N Pearlman Elevation Architects | Architect | C26034 |
| Jacqueline Lingwei Luk Luk And Associates | Engineer | C75724 |
| Donald David Double D Engineering | Engineer | S3928 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025