1530 Page St
San Francisco permit 202112295177 · Haight Ashbury
Renovate to transform st agnes gymnasium main assembly space into a fixed-seated, theatrical hall for performing arts programs, assemblies, & lectures. excavate bsmt area to create an access. music classrm, practice & recording rms, & faculty office. provide mech & strut upgrades & provisions of...
- Filed
- Dec 29, 2021
- Issued
- Aug 9, 2022 (7 months after filing)
- Completed
- Dec 12, 2025 (40 months after issuance)
- Review stops
- 87 stops across 6 departments
- Comments issued
- 11 times, by Public Utilities, Fire Department, Building Inspection
- Put on hold
- 21 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 29, 2021 | Jan 5, 2022 | — |
Zoning review Planning · CP-ZOC | Jan 5, 2022 | Feb 28, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jan 5, 2022 | Aug 3, 2022 | — |
Zoning review Planning · CP-ZOC | Feb 28, 2022 | Jul 29, 2022 | — |
Building plan review Building Inspection · BLDG | Mar 2, 2022 | Jul 8, 2022 | — |
Fire prevention review Fire Department · SFFD | Mar 2, 2022 | Jul 13, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Mar 2, 2022 | Mar 15, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 2, 2022 | Jun 24, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Aug 2, 2022 | Aug 2, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Aug 3, 2022 | Aug 9, 2022 | — |
Addendum 1: Demolition/shoring & underpinning/excavation
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 31, 2022 | Sep 7, 2022 | — |
Building plan review Building Inspection · BLDG | Sep 7, 2022 | Nov 16, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Sep 7, 2022 | Nov 9, 2022 | — |
Permit Processing Center Building Inspection · PPC | Sep 7, 2022 | Dec 8, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Nov 28, 2022 | Dec 5, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 8, 2022 | Dec 21, 2022 | — |
Addendum 2: Structural
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 31, 2022 | Sep 7, 2022 | — |
Building plan review Building Inspection · BLDG | Sep 7, 2022 | Jan 20, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Sep 7, 2022 | Mar 6, 2023 | — |
Permit Processing Center Building Inspection · PPC | Sep 7, 2022 | Mar 7, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Mar 7, 2023 | Mar 9, 2023 | — |
Addendum 3: Architectural/mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 5, 2022 | Dec 5, 2022 | — |
Permit Processing Center Building Inspection · PPC | Dec 5, 2022 | Aug 16, 2023 | — |
Building plan review Building Inspection · BLDG | Dec 9, 2022 | May 10, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 9, 2022 | May 12, 2023 | — |
Fire prevention review Fire Department · SFFD | Dec 9, 2022 | Jun 1, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Dec 9, 2022 | Aug 15, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Dec 9, 2022 | Jan 3, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Jan 30, 2023 | Jun 15, 2023 | — |
Building plan review Building Inspection · BLDG | May 10, 2023 | Jun 22, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | May 12, 2023 | Jun 16, 2023 | — |
Fire prevention review Fire Department · SFFD | Jun 1, 2023 | Aug 2, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Jun 15, 2023 | Jun 15, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 16, 2023 | Jul 20, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 22, 2023 | Jul 18, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Jun 22, 2023 | Jul 5, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 27, 2023 | Jul 28, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 18, 2023 | Jul 25, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 20, 2023 | Jul 26, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Jul 20, 2023 | Jul 21, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 28, 2023 | Jul 28, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Aug 2, 2023 | Aug 2, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 16, 2023 | Aug 18, 2023 | Administrative |
Addendum 4: Fire suppression/sprinklers
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 6, 2023 | Jan 10, 2023 | — |
Fire prevention review Fire Department · SFFD | Jan 10, 2023 | Aug 31, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jan 10, 2023 | Oct 4, 2023 | — |
Fire prevention review Fire Department · SFFD | Sep 26, 2023 | Oct 4, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 4, 2023 | Oct 10, 2023 | Administrative |
Addendum 5: Errcs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 26, 2023 | Apr 26, 2023 | — |
Permit Processing Center Building Inspection · PPC | Apr 26, 2023 | Nov 1, 2023 | Administrative |
Fire prevention review Fire Department · SFFD | Apr 27, 2023 | Aug 8, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 19, 2023 | Oct 10, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 16, 2023 | Oct 19, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 30, 2023 | Oct 31, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 1, 2023 | Nov 7, 2023 | Administrative |
Addendum 6: Metal stairs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 29, 2023 | Nov 29, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Nov 29, 2023 | Jan 26, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 29, 2023 | Apr 16, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Nov 29, 2023 | Jun 17, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jan 29, 2024 | Apr 15, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 15, 2024 | Apr 15, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 14, 2024 | May 20, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 14, 2024 | May 15, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 17, 2024 | Jun 18, 2024 | Administrative |
Addendum 7: Fire alarm
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 21, 2023 | Sep 21, 2023 | Administrative |
Permit Processing Center Building Inspection · PPC | Sep 21, 2023 | May 10, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Sep 22, 2023 | Dec 26, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 21, 2024 | Mar 21, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 10, 2024 | May 10, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 10, 2024 | May 13, 2024 | Administrative |
Addendum 8: Easement
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Sep 24, 2024 | Oct 7, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 27, 2024 | Oct 9, 2024 | Administrative |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 30, 2024 | Sep 30, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Oct 7, 2024 | Oct 7, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Oct 9, 2024 | Oct 9, 2024 | Not Applicable |
Building plan review Building Inspection · BLDG | Oct 9, 2024 | Oct 11, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Oct 9, 2024 | Oct 21, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 9, 2024 | Oct 21, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 21, 2024 | Oct 22, 2024 | Administrative |
Addendum 9: Evac signage
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 24, 2024 | May 7, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Apr 29, 2024 | Apr 29, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Apr 30, 2024 | Apr 30, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | May 7, 2024 | May 7, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 9, 2024 | May 24, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | May 24, 2024 | Jul 9, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | May 24, 2024 | Jul 12, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jul 12, 2024 | Jul 19, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $11,300,000
| Name | Role | License on permit |
|---|---|---|
| William Douaire Bondy Studio Bony Architecture | Architect | C19253 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026