156 Lunado Ct
San Francisco permit 202201045299 · West of Twin Peaks
(n) ev car charger. water service to increase to 11/4" o.d. for (n) fire sprinklers. full interior remodel including: kitchen & 3 bathrms remodels, ramps, sloped walkway, exterior stairs for free accessibility. 78 s.f. addition. remove fireplace/chimney. roofing.(n) windows, mini-split hvac.
- Filed
- Jan 4, 2022
- Issued
- May 17, 2023 (16 months after filing)
- Completed
- Jul 10, 2026 (38 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 19 stops across 5 departments
- Comments issued
- None
- Put on hold
- 6 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 4, 2022 | Jan 5, 2022 | — |
Zoning review Planning · CP-ZOC | Jan 5, 2022 | Jun 14, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jan 5, 2022 | Dec 29, 2022 | — |
Planning neighborhood notice Planning · CP-NP | Jun 15, 2022 | Aug 23, 2022 | — |
Building plan review Building Inspection · BLDG | Aug 24, 2022 | Dec 9, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 24, 2022 | Nov 23, 2022 | — |
Fire prevention review Fire Department · SFFD | Aug 24, 2022 | Dec 9, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Aug 24, 2022 | Oct 26, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 24, 2022 | Sep 2, 2022 | — |
Urban forestry Public Works · DPW-BUF | Nov 1, 2022 | Dec 13, 2022 | — |
Building plan review Building Inspection · BLDG | Nov 22, 2022 | Dec 9, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Nov 28, 2022 | Dec 5, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 28, 2022 | Nov 29, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 8, 2022 | Dec 9, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 8, 2022 | Dec 9, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 8, 2022 | Dec 8, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 22, 2022 | Dec 23, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 22, 2022 | Dec 23, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 29, 2022 | May 17, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $517,000
| Name | Role | License on permit |
|---|---|---|
| James H Neubert James Neubert Architect | Architect | C-27271 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2025