372 Baker St #0
San Francisco permit 202201045301 · Hayes Valley
Fire dmg repair & includes: new roof top mounted heat pumps to condition each unit to replace gas wall heaters, n wall ceiling & floor finishes; n plumbing fix., appliances, n cabinets, n wndws in unit 302 to dmg windows, struct. repair includes replacing localized charred rafter & ceiiling joist on
- Filed
- Jan 4, 2022
- Issued
- Jun 29, 2023 (18 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 15 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 5 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Jan 4, 2022 | Jan 4, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jan 4, 2022 | Apr 5, 2022 | — |
Zoning review Planning · CP-ZOC | Apr 5, 2022 | Oct 28, 2022 | — |
Permit Processing Center Building Inspection · PPC | Apr 5, 2022 | Jun 27, 2023 | — |
Building plan review Building Inspection · BLDG | Oct 31, 2022 | Apr 21, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 31, 2022 | Jun 1, 2023 | — |
Fire prevention review Fire Department · SFFD | Oct 31, 2022 | Jun 7, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 31, 2022 | Nov 7, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Oct 31, 2022 | Jun 21, 2023 | — |
Zoning review Planning · CP-ZOC | Apr 20, 2023 | Jun 1, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 20, 2023 | Apr 20, 2023 | — |
Fire prevention review Fire Department · SFFD | May 30, 2023 | Jun 7, 2023 | — |
Building plan review Building Inspection · BLDG | May 30, 2023 | Jun 6, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 30, 2023 | May 31, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 27, 2023 | Jun 29, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $500,000
| Name | Role | License on permit |
|---|---|---|
| Thornton Weiler Thornton Weiler Aia | Architect | C27685 |
| Albert Urrutia Atrium Structural Engineer | Engineer | S2994 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025