1414 06th Av
San Francisco permit 202201065454 · Inner Sunset
Vertical addition. 2nd fl: (n) library, powder rm, kitchen & dining rm, & rear deck. new 3rd fl: (n) 3 bedrooms, bath, master suite & rear deck. roof: (n) skylights
- Filed
- Jan 6, 2022
- Issued
- Sep 28, 2023 (21 months after filing)
- Completed
- Jun 8, 2026 (32 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 17 stops across 5 departments
- Comments issued
- None
- Put on hold
- 4 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 6, 2022 | Jan 10, 2022 | — |
Zoning review Planning · CP-ZOC | Jan 10, 2022 | Jul 27, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 10, 2022 | Aug 29, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Aug 1, 2022 | Aug 15, 2022 | — |
Building plan review Building Inspection · BLDG | Nov 7, 2022 | Jul 14, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 7, 2022 | Jul 18, 2023 | — |
Fire prevention review Fire Department · SFFD | Nov 7, 2022 | Nov 9, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Nov 7, 2022 | Nov 7, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 7, 2022 | Nov 15, 2022 | — |
Fire prevention review Fire Department · SFFD | Mar 9, 2023 | Mar 10, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 9, 2023 | Aug 21, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 9, 2023 | Mar 23, 2023 | — |
Fire prevention review Fire Department · SFFD | Jul 10, 2023 | Jul 10, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 21, 2023 | Jul 21, 2023 | — |
Fire prevention review Fire Department · SFFD | Aug 21, 2023 | Aug 21, 2023 | Approved |
Development fee collection Building Inspection · DFCU | Aug 22, 2023 | Aug 22, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 29, 2023 | Sep 28, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $497,217
| Name | Role | License on permit |
|---|---|---|
| Sven Erik Lavine Sven Lavine Architecture | Architect | C30122 |
| Sean Thomas Condry Stc Design & Engineering | Engineer | C60860 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022