2741 34th Av
San Francisco permit 202201065469 · Sunset/Parkside
Addition of one detached adu unit at the rear of the building under the state adu program.
- Filed
- Jan 6, 2022
- Issued
- Feb 22, 2023 (14 months after filing)
- Completed
- Jul 7, 2025 (28 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 30 stops across 5 departments
- Comments issued
- Once, by Building Inspection
- Put on hold
- 5 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Planning review Planning · CP-GEN | Jan 6, 2022 | Feb 3, 2022 | — |
Zoning review Planning · CP-ZOC | Feb 3, 2022 | Sep 15, 2022 | — |
Building plan review Building Inspection · BLDG | Feb 3, 2022 | Sep 16, 2022 | — |
Fire prevention review Fire Department · SFFD | Feb 3, 2022 | Feb 17, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Feb 3, 2022 | Feb 7, 2022 | — |
Urban forestry Public Works · DPW-BUF | Feb 3, 2022 | Oct 27, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 3, 2022 | Feb 22, 2022 | — |
Zoning review Planning · CP-ZOC | Apr 5, 2022 | Aug 31, 2022 | — |
Permit Processing Center Building Inspection · PPC | Aug 2, 2022 | Dec 1, 2022 | — |
Fire prevention review Fire Department · SFFD | Sep 21, 2022 | Sep 26, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Sep 21, 2022 | Sep 22, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 21, 2022 | Sep 26, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 31, 2022 | Nov 4, 2022 | — |
Urban forestry Public Works · DPW-BUF | Oct 31, 2022 | Nov 28, 2022 | — |
Development fee collection Building Inspection · DFCU | Oct 31, 2022 | Nov 30, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 1, 2022 | Feb 22, 2023 | — |
Addendum 1: Final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 29, 2023 | Mar 29, 2023 | — |
Permit Processing Center Building Inspection · PPC | Mar 29, 2023 | Nov 29, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Mar 30, 2023 | May 25, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 30, 2023 | Oct 13, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 30, 2023 | Oct 16, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 30, 2023 | Apr 5, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 30, 2023 | Jul 6, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 16, 2023 | Oct 18, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 3, 2023 | Nov 3, 2023 | Approved |
Zoning review Planning · CP-ZOC | Nov 3, 2023 | Nov 15, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Nov 3, 2023 | Nov 8, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 3, 2023 | Nov 28, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 3, 2023 | Nov 7, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 29, 2023 | Dec 21, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Complete
- Estimated cost
- $150,000
| Name | Role | License on permit |
|---|---|---|
| Di Yang Southbay Structure | Engineer | C92766 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022