1011 Turk St
San Francisco permit 202201065473 · Western Addition
T.i. to remodel of second fl including breakroom, dispatch, raised supervisor area, wall relocations and expansion into corridor.
- Filed
- Jan 6, 2022
- Issued
- Dec 6, 2022 (11 months after filing)
- Completed
- Feb 15, 2024 (14 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 17 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 6 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jan 6, 2022 | Jan 6, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jan 18, 2022 | Jan 27, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jan 27, 2022 | Apr 21, 2022 | — |
Building plan review Building Inspection · BLDG | Feb 4, 2022 | Apr 6, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Feb 4, 2022 | Apr 6, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 4, 2022 | Apr 6, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Feb 4, 2022 | Apr 19, 2022 | — |
Public Works disability access review Public Works · PW-DAC | Feb 4, 2022 | Apr 20, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 4, 2022 | Mar 9, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 6, 2022 | Apr 6, 2022 | — |
Building plan review Building Inspection · BLDG | Apr 19, 2022 | Apr 20, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Apr 19, 2022 | Apr 20, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 19, 2022 | Apr 20, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Apr 19, 2022 | Apr 20, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 19, 2022 | Apr 20, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Apr 21, 2022 | Dec 6, 2022 | — |
Public health review Public Health · HEALTH | Jul 15, 2022 | Aug 16, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $4,000,000
| Name | Role | License on permit |
|---|---|---|
| Paul I Cooper Tef Design | Architect | C28490 |
| Jennifer Sadie Tulley Jennifer Tulley Architect | Project contact | C33069 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025