361 Upper Tr
San Francisco permit 202201135971 · Haight Ashbury
Demo: remove rear wall,roof,levl 1 floor/balcony/stair,select demo of interior walls(less than 25%)remove levels 2 and 3 balconies.garage and party walls to remain. floor framing at levels 2, 3, and loft to remain. replace entry stair 1st fl,new deck, stair,and deck/hot tub at grade, new smaller
- Filed
- Jan 13, 2022
- Issued
- May 7, 2024 (28 months after filing)
- Completed
- Sep 23, 2026 (29 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 23 stops across 5 departments
- Comments issued
- 7 times, by Building Inspection
- Put on hold
- 3 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 13, 2022 | Jan 13, 2022 | — |
Zoning review Planning · CP-ZOC | Jan 19, 2022 | Apr 10, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Oct 24, 2022 | Oct 27, 2022 | — |
Permit Processing Center Building Inspection · PPC | Oct 28, 2022 | Apr 26, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Apr 10, 2023 | Apr 10, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 10, 2023 | Jun 7, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 10, 2023 | Jan 24, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 10, 2023 | Apr 10, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 10, 2023 | May 12, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 24, 2024 | Feb 1, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 26, 2024 | Jan 31, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 6, 2024 | Feb 6, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Feb 29, 2024 | Mar 4, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 19, 2024 | Mar 20, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 22, 2024 | Mar 27, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 27, 2024 | Mar 27, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 1, 2024 | Apr 1, 2024 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Apr 1, 2024 | Apr 1, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Apr 2, 2024 | Apr 15, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Apr 3, 2024 | Apr 8, 2024 | Approved |
Zoning review Planning · CP-ZOC | Apr 16, 2024 | Apr 19, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 16, 2024 | Apr 18, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 26, 2024 | May 7, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $750,000
| Name | Role | License on permit |
|---|---|---|
| Kevin Hugo Zeller Zero Ten Design | Architect | C32204 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2020