2545 Greenwich St
San Francisco permit 202201186137 · Marina
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Rev to 201309177050 & 202011219484. revise below grade storage area-increase size by 80 sf. excavation to be <50cy total. lower (e) bldg 24"(leave garage elevation as-is: reduce garage ceiling ht by 24")leave overall ht of addition unchanged. revise front facade materials. remove rear 3rd fl balcony
- Filed
- Jan 18, 2022
- Issued
- Aug 18, 2022 (7 months after filing)
- Completed
- Not completed yet
- Review stops
- 22 stops across 5 departments
- Comments issued
- 3 times, by Building Inspection, Fire Department
- Put on hold
- 3 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 18, 2022 | Jan 27, 2022 | — |
Zoning review Planning · CP-ZOC | Jan 27, 2022 | Mar 14, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jan 27, 2022 | Jun 17, 2022 | — |
Building plan review Building Inspection · BLDG | Mar 15, 2022 | May 5, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Mar 15, 2022 | Mar 15, 2022 | — |
Fire prevention review Fire Department · SFFD | Mar 15, 2022 | Apr 8, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 15, 2022 | Apr 29, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 29, 2022 | Apr 29, 2022 | — |
Building plan review Building Inspection · BLDG | May 10, 2022 | Jun 17, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jun 17, 2022 | Aug 18, 2022 | — |
Addendum 1: Arch structural final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 19, 2023 | May 5, 2023 | — |
Permit Processing Center Building Inspection · PPC | May 5, 2023 | In progress | — |
Building plan review Building Inspection · BLDG | May 8, 2023 | Jan 3, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 8, 2023 | Aug 4, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 8, 2023 | May 17, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 8, 2023 | May 13, 2023 | — |
Fire prevention review Fire Department · SFFD | Sep 15, 2023 | Sep 28, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 15, 2023 | Oct 2, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 15, 2023 | Sep 21, 2023 | Approved |
Building plan review Building Inspection · BLDG | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Cancelled
- Estimated cost
- $50,000
| Name | Role | License on permit |
|---|---|---|
| Marshall Bartz Schneider Schneder Design Associates | Architect | C29499 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2022