405 Howard St #0
San Francisco permit 202201186188 · Financial District/South Beach
Tenant improvement of extg 2nd floor. all work is interior, no exterior or common areas. seperate permit for fire life safety and mep work.
- Filed
- Jan 18, 2022
- Issued
- Apr 20, 2022 (3 months after filing)
- Completed
- Mar 8, 2023 (11 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 10 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Once
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jan 18, 2022 | Jan 18, 2022 | — |
Building plan review Building Inspection · BLDG | Feb 23, 2022 | Feb 23, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 25, 2022 | Feb 25, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 2, 2022 | Mar 2, 2022 | — |
Permit Center Permit Center · PERMIT-CTR | Mar 9, 2022 | Mar 9, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Mar 10, 2022 | Mar 16, 2022 | — |
Zoning review Planning · CP-ZOC | Mar 16, 2022 | Apr 11, 2022 | — |
Fire prevention review Fire Department · SFFD | Apr 12, 2022 | Apr 15, 2022 | — |
Permit Processing Center Building Inspection · PPC | Apr 18, 2022 | Apr 18, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Apr 18, 2022 | Apr 20, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $4,879,800
| Name | Role | License on permit |
|---|---|---|
| Lauren Richardson Jordan Ho+K | Architect | C-36938 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026