11 Wright St
San Francisco permit 202201196236 · Bernal Heights
Rear horizintal addition at 1st/3rd. variance: sec.242(e)(3) mass reduction requirements for rh-1. 1st flr: (n) den & office. 2nd: (n) rear deck. 3rd flr: (n) bed, bath, m, suite(bath & bed), & rear deck. rear yard: (m) stair connection rear yard to 2nd deck.
- Filed
- Jan 19, 2022
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 18 stops across 5 departments
- Comments issued
- Twice, by Public Utilities, Planning
- Put on hold
- Twice
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 19, 2022 | Feb 11, 2022 | — |
Zoning review Planning · CP-ZOC | Feb 11, 2022 | Jan 13, 2023 | — |
Permit Processing Center Building Inspection · PPC | Feb 11, 2022 | Oct 3, 2023 | Administrative |
Planning neighborhood notice Planning · CP-NP | Jul 29, 2022 | Aug 10, 2022 | — |
Building plan review Building Inspection · BLDG | Jan 13, 2023 | Jun 12, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 13, 2023 | Mar 3, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jan 13, 2023 | Jan 18, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 13, 2023 | Feb 22, 2023 | — |
Fire prevention review Fire Department · SFFD | Jul 21, 2023 | Aug 21, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 28, 2023 | Jul 28, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 17, 2023 | Aug 17, 2023 | Approved |
Zoning review Planning · CP-ZOC | Aug 22, 2023 | Aug 24, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 22, 2023 | Sep 14, 2023 | Approved |
Zoning review Planning · CP-ZOC | Sep 12, 2023 | Sep 12, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Sep 15, 2023 | Oct 3, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 15, 2023 | Oct 2, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 15, 2023 | Sep 26, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 3, 2023 | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $380,000
| Name | Role | License on permit |
|---|---|---|
| Sven Erik Lavine Sven Lavine Architecture | Architect | C30122 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025