111 Sutter St #0
San Francisco permit 202201246490 · Financial District/South Beach
10/f: non structural demo a construction of non structural partitions, doors, sidelights, ceilings, power , finishes a millwork.
- Filed
- Jan 24, 2022
- Issued
- Mar 7, 2022 (1 month after filing)
- Completed
- Aug 11, 2022 (5 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2022 were typically issued within 1 month (median of 5,514 issued permits).
- Review stops
- 10 stops across 4 departments
- Comments issued
- Not recorded for this permit
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jan 24, 2022 | Jan 24, 2022 | — |
Building plan review Building Inspection · BLDG | Jan 24, 2022 | Mar 4, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 25, 2022 | Jan 25, 2022 | — |
Intake Building Inspection · INTAKE | Feb 16, 2022 | Feb 16, 2022 | — |
Fire prevention review Fire Department · SFFD | Feb 18, 2022 | Feb 18, 2022 | — |
Zoning review Planning · CP-ZOC | Mar 4, 2022 | Mar 4, 2022 | — |
Building plan review Building Inspection · BLDG | Mar 4, 2022 | Mar 4, 2022 | — |
Fire prevention review Fire Department · SFFD | Mar 4, 2022 | Mar 4, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 4, 2022 | Mar 4, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Mar 7, 2022 | Mar 7, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $591,132
| Name | Role | License on permit |
|---|---|---|
| Rene Garcia Calara Huntsman Arch.Group | Architect | C-30788 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026