360 Spear St
San Francisco permit 202201246538 · Financial District/South Beach
3rd fl: single floor tenant improvement. existing structure, egress staor enclosures to remain. non structural partitions, ceiling, wall and floor finishes only. related mechanical, electrical, plumbing workm change of use from office/internet service exchange to office /laboratory/wholesale sales.
- Filed
- Jan 24, 2022
- Issued
- May 18, 2022 (4 months after filing)
- Completed
- Sep 13, 2023 (16 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2022 were typically issued within 1 month (median of 5,514 issued permits).
- Review stops
- 14 stops across 6 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 3 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jan 24, 2022 | Jan 24, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Feb 11, 2022 | Feb 11, 2022 | — |
Fire prevention review Fire Department · SFFD | Feb 11, 2022 | Feb 11, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Feb 11, 2022 | May 18, 2022 | — |
Building plan review Building Inspection · BLDG | Mar 8, 2022 | Mar 8, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 8, 2022 | Mar 8, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Mar 10, 2022 | Mar 10, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 21, 2022 | Mar 21, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Mar 21, 2022 | Mar 21, 2022 | — |
Public health review Public Health · HEALTH | Apr 1, 2022 | May 3, 2022 | — |
Permit Center Permit Center · PERMIT-CTR | May 4, 2022 | May 4, 2022 | — |
Zoning review Planning · CP-ZOC | May 13, 2022 | May 13, 2022 | — |
Fire prevention review Fire Department · SFFD | May 18, 2022 | May 18, 2022 | — |
Central Permit Bureau Building Inspection · CPB | May 18, 2022 | May 18, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $5,000,000
| Name | Role | License on permit |
|---|---|---|
| Bert Rebuyaco Deviterbo Huntsman Architectural | Architect | C-35090 |
| Blake Dilsworth Kpff Consulting Engineers | Engineer | S3929 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026