600 Montgomery St #0
San Francisco permit 202201266705 · Chinatown
Base building improvement for for fl g1,1,2,3. structural and non-structural demo. construction of new communicating stair. construction of 2 elevators. all associated structural work.
- Filed
- Jan 26, 2022
- Issued
- Apr 21, 2022 (3 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2022 were typically issued within 1 month (median of 5,514 issued permits).
- Review stops
- 10 stops across 5 departments
- Comments issued
- Not recorded for this permit
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jan 26, 2022 | Jan 26, 2022 | — |
Zoning review Planning · CP-ZOC | Feb 1, 2022 | Feb 2, 2022 | — |
Permit Center Permit Center · PERMIT-CTR | Feb 1, 2022 | Feb 1, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 8, 2022 | Feb 8, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Feb 8, 2022 | Feb 8, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Feb 16, 2022 | Feb 16, 2022 | — |
Building plan review Building Inspection · BLDG | Apr 15, 2022 | Apr 15, 2022 | — |
Fire prevention review Fire Department · SFFD | Apr 15, 2022 | Apr 15, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Apr 15, 2022 | Apr 15, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Apr 21, 2022 | Apr 21, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $1,002,978
| Name | Role | License on permit |
|---|---|---|
| Adam Zdzislaw Murphy Huntsman Ag | Architect | C29238 |
| Laura Weyl | Engineer | 6376 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026