272 Naples St
San Francisco permit 202201286871 · Excelsior
2-story 700 sf rear addition with new ground floor master suite including bathrooms, new kitchen, family room, laundry room. new rear deck & stair. 350 sf new ground floor area.
- Filed
- Jan 28, 2022
- Issued
- Mar 20, 2023 (14 months after filing)
- Completed
- Jan 25, 2024 (10 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 23 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 5 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 28, 2022 | Feb 3, 2022 | — |
Zoning review Planning · CP-ZOC | Feb 3, 2022 | Jun 13, 2022 | — |
Permit Processing Center Building Inspection · PPC | Feb 3, 2022 | Feb 22, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Jun 14, 2022 | Jul 25, 2022 | — |
Planning discretionary review Planning · CP-DR | Jul 25, 2022 | Nov 14, 2022 | — |
Building plan review Building Inspection · BLDG | Nov 14, 2022 | Jan 27, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 14, 2022 | Nov 30, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Nov 14, 2022 | Nov 16, 2022 | — |
Building plan review Building Inspection · BLDG | Jan 27, 2023 | Feb 9, 2023 | — |
Zoning review Planning · CP-ZOC | Feb 9, 2023 | Feb 14, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Feb 9, 2023 | Feb 22, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 9, 2023 | Feb 17, 2023 | — |
Building plan review Building Inspection · BLDG | Feb 22, 2023 | Feb 22, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Feb 22, 2023 | Mar 20, 2023 | — |
Addendum 1: Arch, mech, t-24, final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 31, 2023 | Mar 31, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 31, 2023 | Jun 1, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 31, 2023 | Apr 27, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 31, 2023 | Jun 7, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 31, 2023 | Apr 7, 2023 | — |
Permit Processing Center Building Inspection · PPC | Mar 31, 2023 | Jun 9, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 1, 2023 | Jun 1, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 8, 2023 | Jun 15, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 9, 2023 | Jun 9, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $399,411
| Name | Role | License on permit |
|---|---|---|
| Fumiko Eve Docker Pencil Box Architects, Inc | Architect | C33795 |
| Adam Hugo-Holman Degenkolb Engineers | Engineer | S5943 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025