388 Beale St
San Francisco permit 202201286896 · Financial District/South Beach
Change of use - retail to apartments. add 7 units w/ 4 mezz units & (3) 2-story units. 7 units are studios and 1-two bedrm. (n) units are added within envelope at ground level. retain (e) openings, replace (e) storefront glazing w/ new, keep (e) design intent.
- Filed
- Jan 28, 2022
- Issued
- Jul 16, 2024 (30 months after filing)
- Completed
- Jun 16, 2025 (11 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 25 stops across 5 departments
- Comments issued
- Twice, by Fire Department, Building Inspection
- Put on hold
- 5 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Feb 2, 2022 | Feb 2, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Feb 7, 2022 | Feb 7, 2022 | — |
Zoning review Planning · CP-ZOC | Feb 7, 2022 | Mar 27, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jan 25, 2023 | Jan 26, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jan 26, 2023 | Oct 26, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Mar 27, 2023 | Jun 8, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 27, 2023 | Jun 8, 2023 | — |
Fire prevention review Fire Department · SFFD | Mar 27, 2023 | Sep 14, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 27, 2023 | Apr 25, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 27, 2023 | Sep 7, 2023 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Jun 8, 2023 | Jun 12, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 8, 2023 | Jun 9, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 8, 2023 | Jun 15, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 8, 2023 | Jun 15, 2023 | — |
Fire prevention review Fire Department · SFFD | Aug 23, 2023 | Sep 14, 2023 | Approved |
Zoning review Planning · CP-ZOC | Aug 23, 2023 | Sep 28, 2023 | Approved |
Building plan review Building Inspection · BLDG | Aug 23, 2023 | Sep 13, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 23, 2023 | Aug 23, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 23, 2023 | Aug 28, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 13, 2023 | Sep 28, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 13, 2023 | Oct 12, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Sep 13, 2023 | Sep 15, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Oct 16, 2023 | Oct 16, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 16, 2023 | Jul 16, 2024 | Administrative |
Development fee collection Building Inspection · DFCU | Jul 9, 2024 | Jul 9, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $2,661,221
| Name | Role | License on permit |
|---|---|---|
| Toby Stella Levy Levy Design Partners | Architect | C-10527 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025