46 Cragmont Av
San Francisco permit 202201286939 · Inner Sunset
New deck at 3rd floor, remove (e) sunroom, new windows, (e) basement space converted to habitable space.
- Filed
- Jan 28, 2022
- Issued
- Oct 31, 2023 (21 months after filing)
- Completed
- Apr 16, 2025 (18 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 11 stops across 3 departments
- Comments issued
- Twice, by Building Inspection
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 1, 2022 | Feb 1, 2022 | — |
Planning neighborhood notice Planning · CP-NP | Aug 5, 2022 | Nov 3, 2022 | — |
Building plan review Building Inspection · BLDG | Nov 7, 2022 | Aug 3, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 30, 2022 | Aug 1, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 1, 2023 | Feb 2, 2023 | — |
Building plan review Building Inspection · BLDG | Aug 21, 2023 | Aug 21, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 5, 2023 | Sep 5, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 5, 2023 | Sep 11, 2023 | Approved |
Zoning review Planning · CP-ZOC | Sep 11, 2023 | Oct 4, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 5, 2023 | Oct 27, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 27, 2023 | Oct 31, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $160,000
| Name | Role | License on permit |
|---|---|---|
| Lisa Ann Harvey Harvey Architecture | Architect | C23004 |
| Erevan O'neill One Design | Engineer | C75459 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026