1448 Willard St
San Francisco permit 202202017052 · Inner Sunset
Addition & remodel of (e) residential unit & addition of (1) (n) unit.
- Filed
- Feb 1, 2022
- Issued
- Dec 20, 2023 (23 months after filing)
- Completed
- May 6, 2025 (17 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 28 stops across 6 departments
- Comments issued
- 8 times, by Building Inspection, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Feb 1, 2022 | Feb 1, 2022 | — |
Zoning review Planning · CP-ZOC | Feb 1, 2022 | Jun 22, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Jan 20, 2023 | Jan 30, 2023 | — |
Planning discretionary review Planning · CP-DR | Mar 2, 2023 | Jul 27, 2023 | — |
Intake Building Inspection · INTAKE | Jun 23, 2023 | Jun 23, 2023 | — |
Permit Center Permit Center · PERMIT-CTR | Jun 23, 2023 | Jun 23, 2023 | — |
Permit Center Permit Center · PERMIT-CTR | Jun 26, 2023 | Jun 26, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 29, 2023 | Jun 29, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 29, 2023 | Aug 10, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 29, 2023 | Aug 9, 2023 | Issued Comments |
Planning neighborhood notice Planning · CP-NP | Jul 27, 2023 | Jul 27, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 11, 2023 | Aug 31, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 1, 2023 | Sep 1, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 5, 2023 | Sep 20, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 25, 2023 | Sep 26, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 2, 2023 | Oct 10, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 2, 2023 | Oct 10, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 31, 2023 | Nov 9, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 31, 2023 | Nov 9, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 22, 2023 | Nov 27, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 22, 2023 | Nov 27, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 22, 2023 | Nov 22, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Nov 28, 2023 | Dec 4, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 4, 2023 | Dec 12, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 11, 2023 | Dec 12, 2023 | Approved |
Zoning review Planning · CP-ZOC | Dec 12, 2023 | Dec 14, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 18, 2023 | Dec 18, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Dec 18, 2023 | Dec 20, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $210,000
| Name | Role | License on permit |
|---|---|---|
| Calin Smith Smith Engineering, Inc. | Engineer | C57642 |
| Terryl Marshall Lofrano Lofrano Arch/Sculpture Design | Architect | C-7292 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Oct 2017