CheckMyDesigner

1448 Willard St

San Francisco permit 202202017052 · Inner Sunset

Commercial or tenant improvementFull plan reviewComplete
Street view · Oct 2017
Google Street View of 1448 Willard St, Oct 2017
Scope of work
As written on the permit application.

Addition & remodel of (e) residential unit & addition of (1) (n) unit.

Timeline
Key dates from the city record.
Filed
Feb 1, 2022
Issued
Dec 20, 2023 (23 months after filing)
Completed
May 6, 2025 (17 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
28 stops across 6 departments
Comments issued
8 times, by Building Inspection, Public Works
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Feb 1, 2022—

Zoning review

Planning · CP-ZOC

Jun 22, 2023—

Planning neighborhood notice

Planning · CP-NP

Jan 30, 2023—

Planning discretionary review

Planning · CP-DR

Jul 27, 2023—

Intake

Building Inspection · INTAKE

Jun 23, 2023—

Permit Center

Permit Center · PERMIT-CTR

Jun 23, 2023—

Permit Center

Permit Center · PERMIT-CTR

Jun 26, 2023—

Central Permit Bureau

Building Inspection · CPB

Jun 29, 2023—

Building plan review

Building Inspection · BLDG

Aug 10, 2023Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Aug 9, 2023Issued Comments

Planning neighborhood notice

Planning · CP-NP

Jul 27, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Aug 31, 2023Issued Comments

Street use and mapping

Public Works · DPW-BSM

Sep 1, 2023Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Sep 20, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Sep 26, 2023Approved

Building plan review

Building Inspection · BLDG

Oct 10, 2023Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Oct 10, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Nov 9, 2023Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Nov 9, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Nov 27, 2023Approved

Structural plan approval

Building Inspection · PAD-STR

Nov 27, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Nov 22, 2023Approved

Fire prevention review

Fire Department · SFFD

Dec 4, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Dec 12, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 12, 2023Approved

Zoning review

Planning · CP-ZOC

Dec 14, 2023Approved

Permit Processing Center

Building Inspection · PPC

Dec 18, 2023Administrative

Central Permit Bureau

Building Inspection · CPB

Dec 20, 2023Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$210,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Calin Smith

Smith Engineering, Inc.

EngineerC57642
Terryl Marshall Lofrano

Lofrano Arch/Sculpture Design

ArchitectC-7292
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202202017052 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record