53 Nevada St
San Francisco permit 202202017060 · Bernal Heights
Renovation of & horizontal/vertical addition of 2600sq ft to an existing single family residence and will combine two lots. new structure will be a single family home with 4 bedrm, 3.5baths, living/dining space. property will merge 2 lots into one (lots 24 & 25). sprinklers per nfpa 13 sep permit.
- Filed
- Feb 1, 2022
- Issued
- Jan 24, 2025 (36 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 54 stops across 6 departments
- Comments issued
- 14 times, by Building Inspection, Public Works, Fire Department
- Put on hold
- 6 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 1, 2022 | Feb 17, 2022 | — |
Zoning review Planning · CP-ZOC | Feb 17, 2022 | Mar 3, 2022 | — |
Permit Processing Center Building Inspection · PPC | Feb 17, 2022 | Dec 19, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Sep 1, 2022 | May 25, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Sep 1, 2022 | Jun 7, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 1, 2022 | Sep 13, 2022 | — |
Fire prevention review Fire Department · SFFD | Sep 1, 2022 | May 24, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Sep 1, 2022 | Sep 6, 2022 | — |
Urban forestry Public Works · DPW-BUF | Sep 6, 2022 | Aug 7, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 24, 2023 | Jun 30, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | May 24, 2023 | Jun 9, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 24, 2023 | May 26, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 24, 2023 | Apr 8, 2024 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | May 25, 2023 | Jun 8, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 22, 2024 | Mar 29, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 22, 2024 | Mar 28, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Mar 22, 2024 | Jun 21, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Mar 22, 2024 | Apr 1, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Mar 22, 2024 | Jun 20, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 22, 2024 | Mar 29, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 6, 2024 | Jun 6, 2024 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Oct 30, 2024 | Oct 31, 2024 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Oct 30, 2024 | Oct 30, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 30, 2024 | Oct 30, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 30, 2024 | Nov 1, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 30, 2024 | Nov 5, 2024 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Oct 30, 2024 | Dec 18, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Oct 30, 2024 | Nov 5, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Dec 19, 2024 | Dec 19, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Dec 19, 2024 | Jan 24, 2025 | Administrative |
Addendum 1: Final - structural, arch, title 24/mech.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 12, 2025 | Feb 27, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 5, 2025 | Mar 5, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Mar 10, 2025 | Apr 10, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 10, 2025 | Apr 16, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 10, 2025 | Apr 11, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 10, 2025 | Mar 11, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 10, 2025 | Mar 11, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 10, 2025 | Mar 10, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 10, 2025 | In progress | — |
Building plan review quality control Building Inspection · BLDG-QC | Apr 23, 2025 | Apr 23, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jun 24, 2025 | Jun 27, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 24, 2025 | Jul 16, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 24, 2025 | Jul 10, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 24, 2025 | Jun 26, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Jun 24, 2025 | Jun 25, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 24, 2025 | Jun 27, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 29, 2025 | Sep 8, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 29, 2025 | Sep 10, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 29, 2025 | Sep 3, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Aug 29, 2025 | Sep 8, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Aug 29, 2025 | In progress | In Progress |
Public Utilities Commission review Public Utilities · SFPUC | Aug 29, 2025 | Sep 4, 2025 | Approved |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,186,025
| Name | Role | License on permit |
|---|---|---|
| Sarah E Willmer Studio Sarah Willmer | Architect | C29126 |
| Jillian Van Enckevort | Engineer | S5394 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026