4801 03rd St
San Francisco permit 202202027161 · Bayview Hunters Point
New 1-story hcd state approved commercial modualr unit factory built kitchen. (for food service/restaurant use). scope to include site improvements work to site foundations, curbs, paving, mep, as well as scculptural corten steen rain screen enlosure & facade work to prepare for modular unit.
- Filed
- Feb 2, 2022
- Issued
- May 1, 2023 (15 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 17 stops across 6 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 4 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 2, 2022 | Feb 17, 2022 | — |
Zoning review Planning · CP-ZOC | Feb 17, 2022 | May 25, 2022 | — |
Permit Processing Center Building Inspection · PPC | Feb 17, 2022 | Jan 9, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Mar 22, 2022 | Mar 28, 2022 | — |
Building plan review Building Inspection · BLDG | May 25, 2022 | Jul 28, 2022 | — |
Building plan review Building Inspection · BLDG | May 25, 2022 | Dec 13, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | May 25, 2022 | Jan 4, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 25, 2022 | Jun 7, 2022 | — |
Fire prevention review Fire Department · SFFD | May 25, 2022 | Jun 9, 2022 | — |
Street use and mapping Public Works · DPW-BSM | May 25, 2022 | May 31, 2022 | — |
Public health review Public Health · HEALTH | May 25, 2022 | Jun 13, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 6, 2022 | Dec 13, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 13, 2022 | Dec 14, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 21, 2022 | Dec 21, 2022 | — |
Fire prevention review Fire Department · SFFD | Dec 29, 2022 | Dec 29, 2022 | — |
Development fee collection Building Inspection · DFCU | Jan 5, 2023 | Jan 6, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jan 9, 2023 | May 1, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Issued
- Estimated cost
- $200,000
| Name | Role | License on permit |
|---|---|---|
| Irving Antonio Gonzales Gonzales Architects | Architect | C19332 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026