681 12th Av
San Francisco permit 202202117855 · Inner Richmond
Erect 1 story type 5 greenhouse/ceramic studio in rear yard
- Filed
- Feb 11, 2022
- Issued
- Dec 18, 2023 (22 months after filing)
- Completed
- May 4, 2026 (29 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 30 stops across 6 departments
- Comments issued
- 4 times, by Fire Department, Permit Center, Building Inspection, Public Works
- Put on hold
- 3 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Feb 10, 2022 | Feb 22, 2022 | — |
Zoning review Planning · CP-ZOC | Feb 22, 2022 | Mar 23, 2023 | Approved |
Permit Center Permit Center · PERMIT-CTR | Sep 28, 2022 | Sep 28, 2022 | — |
Planning neighborhood notice Planning · CP-NP | Oct 26, 2022 | Dec 14, 2022 | Approved |
Planning discretionary review Planning · CP-DR | Dec 14, 2022 | Mar 2, 2023 | Approved |
Building plan review Building Inspection · BLDG | Mar 27, 2023 | Sep 14, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Sep 15, 2023 | Oct 30, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 3, 2023 | Nov 3, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 3, 2023 | Nov 21, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 21, 2023 | Nov 21, 2023 | Approved |
Zoning review Planning · CP-ZOC | Nov 21, 2023 | Nov 30, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 4, 2023 | Dec 4, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Dec 4, 2023 | Dec 18, 2023 | Administrative |
Addendum 1: Final - ref to boa special condition permit#202403147835
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 25, 2024 | Apr 3, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Mar 26, 2024 | Mar 26, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Apr 3, 2024 | Apr 3, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | May 7, 2024 | May 16, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | May 16, 2024 | May 16, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | May 16, 2024 | May 16, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 16, 2024 | May 16, 2024 | Administrative |
Building plan review Building Inspection · BLDG | May 16, 2024 | Jun 12, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 16, 2024 | Jun 13, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 16, 2024 | Jun 10, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 16, 2024 | May 31, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 16, 2024 | May 23, 2024 | Approved |
Zoning review Planning · CP-ZOC | May 16, 2024 | Aug 12, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | May 16, 2024 | Aug 16, 2024 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Jun 10, 2024 | Jul 29, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 20, 2024 | Jun 20, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 16, 2024 | Sep 6, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Complete
- Estimated cost
- $125,000
| Name | Role | License on permit |
|---|---|---|
| Brent Caldbick Martin Martin Newman Office Llp | Authorized agent-others | C35603 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025