1200 Egbert Av
San Francisco permit 202202147891 · Bayview Hunters Point
To erect a detached, type 5, 2-story, two residential unit building with one state adu unit per government code sect65852.2. (e) front building to remain.
- Filed
- Feb 14, 2022
- Issued
- Sep 22, 2026 (55 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 31 stops across 7 departments
- Comments issued
- 7 times, by Building Inspection, Fire Department
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 14, 2022 | Feb 18, 2022 | — |
Zoning review Planning · CP-ZOC | Feb 18, 2022 | Dec 20, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 18, 2022 | Jul 28, 2026 | Administrative |
Street use and mapping Public Works · DPW-BSM | Mar 14, 2025 | Mar 18, 2025 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Apr 3, 2025 | May 15, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 3, 2025 | May 23, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 3, 2025 | Apr 7, 2025 | Issued Comments |
Public health review Public Health · HEALTH | Apr 3, 2025 | Apr 3, 2025 | Administrative |
Public Health HEALTH-MH | Apr 3, 2025 | Apr 4, 2025 | Not Applicable |
Public Utilities Commission review Public Utilities · SFPUC | Apr 4, 2025 | Apr 17, 2025 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | Apr 4, 2025 | Apr 17, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jun 16, 2025 | Jun 16, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Aug 25, 2025 | Sep 5, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 26, 2025 | Aug 26, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 27, 2025 | Sep 11, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 11, 2025 | Sep 11, 2025 | Issued Comments |
Development fee collection Building Inspection · DFCU | Jan 16, 2026 | Jan 16, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Mar 10, 2026 | Mar 16, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 3, 2026 | Apr 3, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Apr 6, 2026 | Apr 6, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Apr 13, 2026 | Apr 15, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Apr 14, 2026 | May 6, 2026 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Apr 15, 2026 | Apr 16, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 17, 2026 | Apr 24, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 20, 2026 | Apr 20, 2026 | Administrative |
Public Utilities programs review Public Utilities · SFPUC-PRG | Apr 24, 2026 | Apr 24, 2026 | Approved |
Address verification Building Inspection · ADDR | May 21, 2026 | May 28, 2026 | Administrative |
Zoning review Planning · CP-ZOC | May 29, 2026 | Jul 27, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 28, 2026 | Sep 22, 2026 | Administrative |
Addendum 1: Shoring, foundation & framing plan.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 4, 2026 | In progress | In Progress |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Issued
- Estimated cost
- $1,066,873
| Name | Role | License on permit |
|---|---|---|
| Bahman Ghassemzadeh Bahman Ghassenmzadeh | Architect | C75941 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026