342 Moultrie St
San Francisco permit 202202147957 · Bernal Heights
Permit to remove all unpermitted work in 2 car garage for use as garage. per nov.#202058938
- Filed
- Feb 14, 2022
- Issued
- Feb 27, 2024 (24 months after filing)
- Completed
- Aug 21, 2024 (6 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2022 were typically issued within 1 month (median of 5,514 issued permits).
- Review stops
- 13 stops across 3 departments
- Comments issued
- Twice, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building inspector Building Inspection · BID-INSP | Feb 14, 2022 | Feb 14, 2022 | — |
Intake Building Inspection · INTAKE | Feb 14, 2022 | Feb 14, 2022 | — |
Zoning review Planning · CP-ZOC | Feb 14, 2022 | Dec 14, 2023 | Approved |
Permit Center Permit Center · PERMIT-CTR | Aug 7, 2023 | Aug 7, 2023 | — |
Zoning review Planning · CP-ZOC | Dec 14, 2023 | Dec 14, 2023 | Approved |
Building plan review Building Inspection · BLDG | Dec 14, 2023 | Dec 14, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 18, 2024 | Jan 18, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 26, 2024 | Feb 26, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 26, 2024 | Feb 26, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 26, 2024 | Feb 26, 2024 | Approved |
Zoning review Planning · CP-ZOC | Feb 26, 2024 | Feb 26, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Feb 26, 2024 | Feb 26, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 27, 2024 | Feb 27, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $41,000
| Name | Role | License on permit |
|---|---|---|
| Kieran J Boughan Kieran Boughan | Architect | C18064 |
| Gregory Paul Wallace | Engineer | S-3308 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2016