1520 Stockton St
San Francisco permit 202202158007 · North Beach
Att: install 3 new antennas; install 9 new rrus; remove 2 extg cabinets; install new equipment rack with batteries; no electrical work.
- Filed
- Feb 15, 2022
- Issued
- Feb 7, 2024 (24 months after filing)
- Completed
- Nov 27, 2024 (10 months after issuance)
- Review stops
- 10 stops across 4 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Feb 15, 2022 | Feb 15, 2022 | — |
Zoning review Planning · CP-ZOC | Feb 17, 2022 | Feb 17, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 17, 2022 | Feb 17, 2022 | — |
Intake Building Inspection · INTAKE | Mar 8, 2022 | Mar 8, 2022 | — |
Zoning review Planning · CP-ZOC | Mar 8, 2022 | Mar 8, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Mar 10, 2022 | Mar 10, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 10, 2022 | Mar 10, 2022 | — |
Fire prevention review Fire Department · SFFD | Mar 10, 2022 | Mar 10, 2022 | — |
Public health review Public Health · HEALTH | Mar 10, 2022 | Mar 10, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Feb 7, 2024 | Feb 7, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $53,000
| Name | Role | License on permit |
|---|---|---|
| Chris Lee Interlocity | Engineer | 76549 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026