CheckMyDesigner

25 Bennington St

San Francisco permit 202202158037 · Bernal Heights

AdditionFull plan reviewComplete
Street view · Feb 2022
Google Street View of 25 Bennington St, Feb 2022
Scope of work
As written on the permit application.

Remove 1-story rear addition & replace w/ 3-story addition. excavate @ rear garage to create 1st fl living space. relocate (e) 2nd fl kitchen & bathroom, add 2 dommers, 2 bedrooms, 1 bath, skylight, & balcony @ 3rd fl. build ((n) interior stair. add spiral stair & patio @ rear

Timeline
Key dates from the city record.
Filed
Feb 15, 2022
Issued
Nov 14, 2023 (21 months after filing)
Completed
Dec 2, 2025 (25 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
23 stops across 5 departments
Comments issued
4 times, by Building Inspection, Fire Department, Public Utilities
Put on hold
Twice

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Feb 23, 2022—

Central Permit Bureau

Building Inspection · CPB

Mar 2, 2022—

Zoning review

Planning · CP-ZOC

Aug 21, 2023Approved

Planning neighborhood notice

Planning · CP-NP

Jun 8, 2023Administrative

Building plan review

Building Inspection · BLDG

Sep 14, 2023Issued Comments

Fire prevention review

Fire Department · SFFD

Sep 25, 2023Issued Comments

Street use and mapping

Public Works · DPW-BSM

Sep 29, 2023Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Oct 13, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Oct 19, 2023Approved

Fire prevention review

Fire Department · SFFD

Oct 30, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 31, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Nov 3, 2023Approved

Zoning review

Planning · CP-ZOC

Nov 6, 2023Approved

Permit Processing Center

Building Inspection · PPC

Nov 7, 2023Administrative

Central Permit Bureau

Building Inspection · CPB

Nov 14, 2023Administrative

Addendum 1: Final - arch,struct,t-24.

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Nov 22, 2023Administrative

Building plan review

Building Inspection · BLDG

Jan 24, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Feb 1, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Feb 2, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Feb 6, 2024Approved

Building plan review

Building Inspection · BLDG

Mar 8, 2024Approved

Permit Processing Center

Building Inspection · PPC

Mar 8, 2024Administrative

Central Permit Bureau

Building Inspection · CPB

Apr 16, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$575,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Mark Reilly

Mark Reilly Architecture

ArchitectC-33112
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202202158037 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record