25 Bennington St
San Francisco permit 202202158037 · Bernal Heights
Remove 1-story rear addition & replace w/ 3-story addition. excavate @ rear garage to create 1st fl living space. relocate (e) 2nd fl kitchen & bathroom, add 2 dommers, 2 bedrooms, 1 bath, skylight, & balcony @ 3rd fl. build ((n) interior stair. add spiral stair & patio @ rear
- Filed
- Feb 15, 2022
- Issued
- Nov 14, 2023 (21 months after filing)
- Completed
- Dec 2, 2025 (25 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 23 stops across 5 departments
- Comments issued
- 4 times, by Building Inspection, Fire Department, Public Utilities
- Put on hold
- Twice
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 15, 2022 | Feb 23, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Feb 28, 2022 | Mar 2, 2022 | — |
Zoning review Planning · CP-ZOC | Mar 2, 2022 | Aug 21, 2023 | Approved |
Planning neighborhood notice Planning · CP-NP | Apr 20, 2023 | Jun 8, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Aug 22, 2023 | Sep 14, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 14, 2023 | Sep 25, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 28, 2023 | Sep 29, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Oct 2, 2023 | Oct 13, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 13, 2023 | Oct 19, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Oct 19, 2023 | Oct 30, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 30, 2023 | Oct 31, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 31, 2023 | Nov 3, 2023 | Approved |
Zoning review Planning · CP-ZOC | Nov 6, 2023 | Nov 6, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 7, 2023 | Nov 7, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Nov 7, 2023 | Nov 14, 2023 | Administrative |
Addendum 1: Final - arch,struct,t-24.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 22, 2023 | Nov 22, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Nov 22, 2023 | Jan 24, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 26, 2024 | Feb 1, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 1, 2024 | Feb 2, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 5, 2024 | Feb 6, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 6, 2024 | Mar 8, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 8, 2024 | Mar 8, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 8, 2024 | Apr 16, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $575,000
| Name | Role | License on permit |
|---|---|---|
| Mark Reilly Mark Reilly Architecture | Architect | C-33112 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2022