1035 Filbert St
San Francisco permit 202202248655 · Russian Hill
Replace (e) deck with (n) deck.
- Filed
- Feb 24, 2022
- Issued
- Nov 7, 2022 (8 months after filing)
- Completed
- Feb 8, 2023 (3 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2022 were typically issued within 1 month (median of 5,514 issued permits).
- Review stops
- 5 stops across 3 departments
- Comments issued
- Not recorded for this permit
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Feb 24, 2022 | Feb 24, 2022 | — |
Zoning review Planning · CP-ZOC | Feb 28, 2022 | Aug 12, 2022 | — |
Permit Center Permit Center · PERMIT-CTR | Aug 12, 2022 | Aug 12, 2022 | — |
Building plan review Building Inspection · BLDG | Aug 24, 2022 | Aug 24, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Nov 7, 2022 | Nov 7, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $20,000
| Name | Role | License on permit |
|---|---|---|
| David R Teeters | Architect | C11720 |
| Nikica Favretto Ftf Engineering Inc. | Engineer | C-83339 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022