1373 San Bruno Av
San Francisco permit 202202258750 · Mission
Add 1 office/den and 1 bathroom on ground; add 1 bathroom on second floor. stair penthouse access new roof deck.
- Filed
- Feb 25, 2022
- Issued
- Mar 16, 2026 (49 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 46 stops across 4 departments
- Comments issued
- 7 times, by Planning, Building Inspection, Public Utilities
- Put on hold
- 3 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 25, 2022 | Mar 16, 2022 | Administrative |
Building inspector Building Inspection · BID-INSP | Mar 10, 2022 | Mar 10, 2022 | — |
Code enforcement Building Inspection · CES | Mar 15, 2022 | Mar 15, 2022 | — |
Zoning review Planning · CP-ZOC | Mar 16, 2022 | Sep 15, 2022 | — |
Permit Processing Center Building Inspection · PPC | Mar 16, 2022 | Oct 14, 2025 | Administrative |
Planning neighborhood notice Planning · CP-NP | Jul 29, 2022 | Jul 29, 2022 | — |
Building plan review Building Inspection · BLDG | Sep 20, 2022 | Feb 28, 2023 | — |
Building plan review Building Inspection · BLDG | Sep 20, 2022 | Mar 15, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 20, 2022 | Mar 3, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Sep 20, 2022 | Sep 20, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 20, 2022 | Oct 17, 2022 | — |
Zoning review Planning · CP-ZOC | Mar 3, 2023 | Mar 6, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 3, 2023 | Mar 3, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 3, 2023 | Mar 9, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 3, 2023 | Mar 6, 2023 | — |
Building inspector Building Inspection · BID-INSP | Mar 13, 2023 | Mar 13, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 22, 2023 | Mar 22, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 22, 2023 | May 16, 2023 | — |
Zoning review Planning · CP-ZOC | Nov 9, 2023 | Nov 9, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 1, 2024 | Aug 1, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 1, 2024 | Aug 13, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 1, 2024 | Aug 16, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 1, 2024 | Aug 1, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 1, 2024 | Aug 5, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 5, 2024 | Aug 5, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jun 23, 2025 | Jun 23, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jun 23, 2025 | Jul 1, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 23, 2025 | Jul 16, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 23, 2025 | Jun 25, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 23, 2025 | Jun 27, 2025 | Approved |
Zoning review Planning · CP-ZOC | Aug 20, 2025 | Aug 26, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 20, 2025 | Aug 29, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 20, 2025 | Sep 12, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 20, 2025 | Aug 21, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 20, 2025 | Sep 3, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Sep 16, 2025 | Sep 16, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 16, 2025 | Sep 26, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 16, 2025 | Sep 29, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 16, 2025 | Sep 19, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 16, 2025 | Sep 18, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 2, 2025 | Oct 3, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 2, 2025 | Oct 14, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 2, 2025 | Oct 3, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 2, 2025 | Oct 6, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 2, 2025 | Oct 14, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 14, 2025 | Mar 16, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $100,000
| Name | Role | License on permit |
|---|---|---|
| Thomas Steven Podesta Thomas Podesta Engineer | Engineer | C-37028 |
| John C Lee John C Lee | Architect | C6896 |
| Rodrigo Santos Rs Engineering | Engineer | S2984 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2022