CheckMyDesigner

2255 03rd St

San Francisco permit 202202258768 · Potrero Hill

Commercial or tenant improvementFull plan reviewFiled
Street view · Feb 2025
Google Street View of 2255 03rd St, Feb 2025
Scope of work
As written on the permit application.

Change of use type b occ to type e for 2-8 school. new accessible women's restroom @ lower level. remodel (e) restroom, (n) plumbing fixtures, drinking fountain/bottle filler. relocate kitchenette. mech/fire life safety system will be modified as needed.

Timeline
Key dates from the city record.
Filed
Feb 25, 2022
Issued
Not issued yet
Completed
Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
30 stops across 7 departments
Comments issued
9 times, by Building Inspection, Fire Department, Public Works, Public Utilities, Public Health
Put on hold
Twice
Review stopFinishedResult

Intake

Building Inspection · INTAKE

Feb 25, 2022—

Zoning review

Planning · CP-ZOC

Aug 3, 2022Approved

Planning neighborhood notice

Planning · CP-NP

Jul 19, 2022Approved

Intake

Building Inspection · INTAKE

Aug 2, 2022—

Planning neighborhood notice

Planning · CP-NP

Aug 3, 2022Approved

Permit Center

Permit Center · PERMIT-CTR

Aug 3, 2022—

Building plan review

Building Inspection · BLDG

Aug 5, 2022—

Permit Center

Permit Center · PERMIT-CTR

Aug 5, 2022—

Central Permit Bureau

Building Inspection · CPB

Sep 14, 2022—

Building plan review

Building Inspection · BLDG

Mar 8, 2024Issued Comments

Building plan review

Building Inspection · BLDG

May 7, 2024Administrative

Building plan review

Building Inspection · BLDG

May 7, 2024Issued Comments

Building plan review quality control

Building Inspection · BLDG-QC

May 7, 2024Administrative

Mechanical and energy plan review

Building Inspection · MECH

Jun 24, 2024Issued Comments

Building plan review

Building Inspection · BLDG

May 17, 2024Approved

Fire prevention review

Fire Department · SFFD

Aug 6, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jul 23, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Aug 8, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Aug 20, 2024Issued Comments

Public health review

Public Health · HEALTH

Sep 4, 2024Issued Comments

Public Health

HEALTH-MH

Sep 3, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

In progress—

Fire prevention review

Fire Department · SFFD

In progress—

Street use and mapping

Public Works · DPW-BSM

In progress—

Public Utilities Commission review

Public Utilities · SFPUC

In progress—

Public health review

Public Health · HEALTH

In progress—

Public Health

HEALTH-MH

In progress—

Development fee collection

Building Inspection · DFCU

In progress—

Permit Processing Center

Building Inspection · PPC

In progress—

Central Permit Bureau

Building Inspection · CPB

In progress—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Filed
Estimated cost
$150,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Pauline Margaret Souza

Wrbs Studio

ArchitectC24532
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202202258768 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record