2255 03rd St
San Francisco permit 202202258768 · Potrero Hill
Change of use type b occ to type e for 2-8 school. new accessible women's restroom @ lower level. remodel (e) restroom, (n) plumbing fixtures, drinking fountain/bottle filler. relocate kitchenette. mech/fire life safety system will be modified as needed.
- Filed
- Feb 25, 2022
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 30 stops across 7 departments
- Comments issued
- 9 times, by Building Inspection, Fire Department, Public Works, Public Utilities, Public Health
- Put on hold
- Twice
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Feb 25, 2022 | Feb 25, 2022 | — |
Zoning review Planning · CP-ZOC | Mar 3, 2022 | Aug 3, 2022 | Approved |
Planning neighborhood notice Planning · CP-NP | Jun 6, 2022 | Jul 19, 2022 | Approved |
Intake Building Inspection · INTAKE | Aug 2, 2022 | Aug 2, 2022 | — |
Planning neighborhood notice Planning · CP-NP | Aug 3, 2022 | Aug 3, 2022 | Approved |
Permit Center Permit Center · PERMIT-CTR | Aug 3, 2022 | Aug 3, 2022 | — |
Building plan review Building Inspection · BLDG | Aug 5, 2022 | Aug 5, 2022 | — |
Permit Center Permit Center · PERMIT-CTR | Aug 5, 2022 | Aug 5, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Aug 10, 2022 | Sep 14, 2022 | — |
Building plan review Building Inspection · BLDG | Sep 14, 2022 | Mar 8, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 14, 2022 | May 7, 2024 | Administrative |
Building plan review Building Inspection · BLDG | May 7, 2024 | May 7, 2024 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | May 7, 2024 | May 7, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | May 16, 2024 | Jun 24, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 17, 2024 | May 17, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jun 20, 2024 | Aug 6, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 8, 2024 | Jul 23, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 6, 2024 | Aug 8, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 9, 2024 | Aug 20, 2024 | Issued Comments |
Public health review Public Health · HEALTH | Aug 20, 2024 | Sep 4, 2024 | Issued Comments |
Public Health HEALTH-MH | Sep 3, 2024 | Sep 3, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | — | In progress | — |
Public health review Public Health · HEALTH | — | In progress | — |
Public Health HEALTH-MH | — | In progress | — |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Permit Processing Center Building Inspection · PPC | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Filed
- Estimated cost
- $150,000
| Name | Role | License on permit |
|---|---|---|
| Pauline Margaret Souza Wrbs Studio | Architect | C24532 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025