San Francisco permit 202202288805 · North Beach

Home remodel (type unconfirmed)Full plan reviewIssued
Street view · Jan 2025
Google Street View of 2231 Powell St #0, Jan 2025
Scope of work
As written on the permit application.

Reconstruction of (e)fire damaged units @ 2nd & 3rd fls with modification to floor plans.all work to be performed withing(e)boundary of the bldg.removal of(e)metal fire escapes.partially addressed nov#202047402.conversion of 4 carpots to one adu(under separate permit)

Timeline
Key dates from the city record.
Filed
Feb 28, 2022
Issued
May 7, 2024 (26 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
32 stops across 5 departments
Comments issued
6 times, by Building Inspection, Fire Department
Put on hold
3 times
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Mar 22, 2022—

Zoning review

Planning · CP-ZOC

Aug 10, 2022—

Code enforcement

Building Inspection · CES

Mar 29, 2022—

Permit Processing Center

Building Inspection · PPC

May 6, 2024Administrative

Building plan review

Building Inspection · BLDG

Jul 26, 2023Issued Comments

Fire prevention review

Fire Department · SFFD

Aug 7, 2023—

Street use and mapping

Public Works · DPW-BSM

Oct 24, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Aug 18, 2022—

Zoning review

Planning · CP-ZOC

Jul 21, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Jul 27, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 7, 2023Issued Comments

Fire prevention review

Fire Department · SFFD

Aug 8, 2023Issued Comments

Street use and mapping

Public Works · DPW-BSM

Oct 26, 2023—

Fire prevention review

Fire Department · SFFD

Dec 19, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Dec 20, 2023Approved

Building plan review

Building Inspection · BLDG

Dec 27, 2023Approved

Fire prevention review

Fire Department · SFFD

Jan 3, 2024Approved-Stipulated

Zoning review

Planning · CP-ZOC

Jan 8, 2024Approved

Building plan review

Building Inspection · BLDG

Jan 17, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jan 24, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jan 10, 2024Approved

Building plan review

Building Inspection · BLDG

Feb 8, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Apr 16, 2024Issued Comments

Urban forestry

Public Works · DPW-BUF

Apr 17, 2024Approved

Building plan review

Building Inspection · BLDG

Apr 25, 2024Approved

Zoning review

Planning · CP-ZOC

May 3, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Apr 29, 2024Approved

Fire prevention review

Fire Department · SFFD

Apr 30, 2024Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

May 1, 2024Approved

Urban forestry

Public Works · DPW-BUF

Apr 26, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

May 1, 2024Approved

Central Permit Bureau

Building Inspection · CPB

May 7, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$1,500,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Bahman Ghassemzadeh

Bahman Ghassenmzadeh

EngineerC75941
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202202288805 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record