CheckMyDesigner

7 Winfield St

San Francisco permit 202202288899 · Bernal Heights

AdditionFull plan reviewComplete
Street view · Feb 2022
Google Street View of 7 Winfield St, Feb 2022
Scope of work
As written on the permit application.

Interior remodel of main (2nd) fl - inclding new kitchen, 1/2 bath, new windows & doors on non-street facing. vertical addition of a 3rd fl with additional bedrm, bathrm, office/guest space, & roof deck.

Timeline
Key dates from the city record.
Filed
Feb 28, 2022
Issued
Apr 28, 2023 (14 months after filing)
Completed
Aug 5, 2025 (27 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
30 stops across 5 departments
Comments issued
3 times, by Building Inspection
Put on hold
6 times

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Apr 4, 2022—

Zoning review

Planning · CP-ZOC

Sep 15, 2022—

Permit Processing Center

Building Inspection · PPC

Feb 28, 2023—

Planning neighborhood notice

Planning · CP-NP

Aug 2, 2022—

Building plan review

Building Inspection · BLDG

Dec 21, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Oct 7, 2022—

Fire prevention review

Fire Department · SFFD

Sep 16, 2022—

Street use and mapping

Public Works · DPW-BSM

Sep 16, 2022—

Zoning review

Planning · CP-ZOC

Feb 23, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Dec 7, 2022—

Fire prevention review

Fire Department · SFFD

Dec 23, 2022Approved

Street use and mapping

Public Works · DPW-BSM

Feb 27, 2023—

Central Permit Bureau

Building Inspection · CPB

Apr 28, 2023—

Addendum 1: Arch, structrual, final plans

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

May 11, 2023—

Building plan review

Building Inspection · BLDG

Aug 11, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Aug 11, 2023—

Fire prevention review

Fire Department · SFFD

Oct 4, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Oct 16, 2023Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

May 18, 2023—

Permit Processing Center

Building Inspection · PPC

Oct 18, 2023Administrative

Building plan review

Building Inspection · BLDG

Aug 15, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Aug 21, 2023Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Aug 17, 2023Approved

Building plan review

Building Inspection · BLDG

Sep 19, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Sep 14, 2023Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Sep 14, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Oct 4, 2023Approved

Building plan review

Building Inspection · BLDG

Oct 12, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 10, 2023Approved

Central Permit Bureau

Building Inspection · CPB

Oct 23, 2023Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$437,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
John Bonner Kleman

Light Space Architecture

ArchitectC36418
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202202288899 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record