7 Winfield St
San Francisco permit 202202288899 · Bernal Heights
Interior remodel of main (2nd) fl - inclding new kitchen, 1/2 bath, new windows & doors on non-street facing. vertical addition of a 3rd fl with additional bedrm, bathrm, office/guest space, & roof deck.
- Filed
- Feb 28, 2022
- Issued
- Apr 28, 2023 (14 months after filing)
- Completed
- Aug 5, 2025 (27 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 30 stops across 5 departments
- Comments issued
- 3 times, by Building Inspection
- Put on hold
- 6 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 28, 2022 | Apr 4, 2022 | — |
Zoning review Planning · CP-ZOC | Apr 4, 2022 | Sep 15, 2022 | — |
Permit Processing Center Building Inspection · PPC | Apr 4, 2022 | Feb 28, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Jul 29, 2022 | Aug 2, 2022 | — |
Building plan review Building Inspection · BLDG | Sep 15, 2022 | Dec 21, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 15, 2022 | Oct 7, 2022 | — |
Fire prevention review Fire Department · SFFD | Sep 15, 2022 | Sep 16, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Sep 15, 2022 | Sep 16, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 2, 2022 | Feb 23, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 2, 2022 | Dec 7, 2022 | — |
Fire prevention review Fire Department · SFFD | Dec 2, 2022 | Dec 23, 2022 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 2, 2022 | Feb 27, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Feb 28, 2023 | Apr 28, 2023 | — |
Addendum 1: Arch, structrual, final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 11, 2023 | May 11, 2023 | — |
Building plan review Building Inspection · BLDG | May 12, 2023 | Aug 11, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | May 12, 2023 | Aug 11, 2023 | — |
Fire prevention review Fire Department · SFFD | May 12, 2023 | Oct 4, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | May 12, 2023 | Oct 16, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | May 12, 2023 | May 18, 2023 | — |
Permit Processing Center Building Inspection · PPC | May 12, 2023 | Oct 18, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Aug 11, 2023 | Aug 15, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 11, 2023 | Aug 21, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 11, 2023 | Aug 17, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 11, 2023 | Sep 19, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 14, 2023 | Sep 14, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 14, 2023 | Sep 14, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 4, 2023 | Oct 4, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 4, 2023 | Oct 12, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 4, 2023 | Oct 10, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 18, 2023 | Oct 23, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $437,000
| Name | Role | License on permit |
|---|---|---|
| John Bonner Kleman Light Space Architecture | Architect | C36418 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2022