50 08th St
San Francisco permit 202203029052 · South of Market
Multifunctional to an extg verizon site: remove 2 extg antennas. remove 4 extg rrus11 b13+a2. remove 4 extg dc-3315 surge protectors. install 2 new antennas. install 4 new rru 4449. install 4 new dc-6627 surge protectors.
- Filed
- Mar 2, 2022
- Issued
- Jan 20, 2023 (11 months after filing)
- Completed
- Mar 21, 2023 (2 months after issuance)
- Review stops
- 11 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Once
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Mar 2, 2022 | Mar 2, 2022 | — |
Building inspector Building Inspection · BID-INSP | Mar 2, 2022 | Mar 2, 2022 | — |
Intake Building Inspection · INTAKE | Mar 2, 2022 | Mar 2, 2022 | — |
Zoning review Planning · CP-ZOC | Mar 2, 2022 | Dec 19, 2022 | — |
Building plan review Building Inspection · BLDG | Nov 18, 2022 | Nov 18, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 18, 2022 | Nov 18, 2022 | — |
Fire prevention review Fire Department · SFFD | Dec 19, 2022 | Dec 19, 2022 | — |
Fire prevention review Fire Department · SFFD | Dec 19, 2022 | Dec 19, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Dec 19, 2022 | Dec 19, 2022 | — |
Public health review Public Health · HEALTH | Dec 19, 2022 | Dec 21, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jan 20, 2023 | Jan 20, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $40,000
| Name | Role | License on permit |
|---|---|---|
| Esra Persellin Leaf Communications | Engineer | C88844 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026