1558 Grove St
San Francisco permit 202203079335 · Lone Mountain/USF
Ground floor expansion at rear and dormer at stair.
- Filed
- Mar 7, 2022
- Issued
- Apr 12, 2023 (13 months after filing)
- Completed
- May 16, 2025 (25 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 20 stops across 4 departments
- Comments issued
- None
- Put on hold
- Twice
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 7, 2022 | Mar 10, 2022 | — |
Zoning review Planning · CP-ZOC | Mar 10, 2022 | Jan 30, 2023 | — |
Permit Processing Center Building Inspection · PPC | Mar 10, 2022 | Apr 6, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Dec 12, 2022 | Jan 30, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 30, 2023 | Mar 30, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 30, 2023 | Feb 23, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jan 30, 2023 | Feb 1, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 30, 2023 | Mar 30, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 30, 2023 | Apr 5, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Apr 6, 2023 | Apr 12, 2023 | — |
Addendum 1: Struct,arch,mep,final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 24, 2023 | Apr 24, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 24, 2023 | Jun 27, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 24, 2023 | May 17, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Apr 24, 2023 | Apr 26, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 24, 2023 | May 5, 2023 | — |
Permit Processing Center Building Inspection · PPC | Apr 24, 2023 | Aug 7, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 28, 2023 | Jul 11, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 28, 2023 | Aug 3, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 28, 2023 | Jul 6, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Aug 7, 2023 | Aug 11, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $194,809
| Name | Role | License on permit |
|---|---|---|
| Federico Engel Butler Armsden Architecture | Architect | C32207 |
| Adam Frederick Klein Bkg Structural Engineers | Engineer | S5941 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2025