650 Linden St
San Francisco permit 202203079351 · Hayes Valley
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision for scope market by mod as "deferred approval" on sheet l103 + l700 during permit review. scope is limited to accessible paths for pa# 201912270759, 201912270764, 201912270766, 201912270767, 201912270768, 201912270769.
- Filed
- Mar 7, 2022
- Issued
- Jun 16, 2022 (3 months after filing)
- Completed
- Not completed yet
- Review stops
- 10 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Once
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building inspector Building Inspection · BID-INSP | Mar 7, 2022 | Mar 7, 2022 | — |
Apartment and hotel inspection Building Inspection · HIS | Mar 7, 2022 | Mar 7, 2022 | — |
Plumbing inspector Building Inspection · PID-INSP | Mar 7, 2022 | Mar 7, 2022 | — |
Intake Building Inspection · INTAKE | Mar 7, 2022 | Mar 7, 2022 | — |
Building plan review Building Inspection · BLDG | Mar 7, 2022 | Mar 7, 2022 | — |
Fire prevention review Fire Department · SFFD | Mar 7, 2022 | Mar 7, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Mar 8, 2022 | Mar 8, 2022 | — |
Disability access review Mayor's Office on Disability · MOD | Mar 10, 2022 | Jun 13, 2022 | — |
Zoning review Planning · CP-ZOC | Jun 15, 2022 | Jun 15, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jun 16, 2022 | Jun 16, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Pamela Anne Collier Levy Design Partners | Architect | C14940 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025