1 South Van Ness Av
San Francisco permit 202203079381 · Mission
Priority prj-modernize 3 (e) elevators: replace/refurbish (e) equipment, car control panels& lobby fixtures.upgrade elevator call system of passenger elevators to destination dispatch system & provide emergency 2-way/ visual based, text based interactive communication system in cab control panels.
- Filed
- Mar 7, 2022
- Issued
- Aug 3, 2023 (17 months after filing)
- Completed
- Not completed yet
- Review stops
- 18 stops across 3 departments
- Comments issued
- None
- Put on hold
- 6 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 7, 2022 | Mar 15, 2022 | — |
Building plan review Building Inspection · BLDG | Mar 15, 2022 | Feb 16, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 15, 2022 | Mar 13, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Mar 15, 2022 | Apr 12, 2023 | — |
Fire prevention review Fire Department · SFFD | Mar 15, 2022 | Mar 21, 2023 | — |
Public Works disability access review Public Works · PW-DAC | Mar 15, 2022 | Feb 16, 2023 | — |
Permit Processing Center Building Inspection · PPC | Mar 15, 2022 | Apr 21, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Apr 25, 2022 | Apr 26, 2022 | — |
Building plan review Building Inspection · BLDG | Feb 16, 2023 | Mar 31, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Feb 16, 2023 | Feb 22, 2023 | — |
Public Works disability access review Public Works · PW-DAC | Feb 16, 2023 | Mar 10, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 31, 2023 | Apr 5, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 31, 2023 | Apr 5, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Mar 31, 2023 | Apr 4, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 31, 2023 | Apr 6, 2023 | — |
Fire prevention review Fire Department · SFFD | Mar 31, 2023 | Apr 18, 2023 | — |
Public Works disability access review Public Works · PW-DAC | Mar 31, 2023 | Apr 10, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Apr 21, 2023 | Aug 3, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,226,500
| Name | Role | License on permit |
|---|---|---|
| Paul I Cooper Tef Design | Architect | C28490 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026