1200 15th St
San Francisco permit 202203089442 · Mission
Renovate, rehab & seisimically retrofit (e) 2-story, 29500 sf building to provide office and operational space for sfmta parking & traffic enforcement division. install a standard office trailer @ adjacent vacant parcel under pa 202401234496 to house the division's emergency related operations.
- Filed
- Mar 8, 2022
- Issued
- Feb 11, 2025 (35 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 106 stops across 7 departments
- Comments issued
- 38 times, by Building Inspection, Fire Department, Public Works, Public Utilities, Public Health
- Put on hold
- 5 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 8, 2022 | Mar 15, 2022 | — |
Zoning review Planning · CP-ZOC | Mar 15, 2022 | Mar 29, 2022 | — |
Permit Processing Center Building Inspection · PPC | Mar 15, 2022 | Dec 6, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Mar 29, 2022 | Jun 16, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 29, 2022 | Jan 10, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 29, 2022 | Apr 14, 2022 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 29, 2022 | Apr 27, 2022 | — |
Public Works disability access review Public Works · PW-DAC | Mar 29, 2022 | Apr 28, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 29, 2022 | Apr 26, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 29, 2022 | May 11, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Apr 29, 2022 | Aug 25, 2022 | — |
Zoning review Planning · CP-ZOC | Apr 29, 2022 | Oct 7, 2024 | Approved |
Public Works disability access review Public Works · PW-DAC | Apr 27, 2023 | Apr 28, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 27, 2023 | Oct 8, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 27, 2023 | Nov 1, 2023 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Apr 27, 2023 | May 18, 2023 | Issued Comments |
Public Works disability access review Public Works · PW-DAC | Jan 4, 2024 | Jan 5, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jan 4, 2024 | Feb 29, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 4, 2024 | Jan 18, 2024 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Sep 23, 2024 | Sep 25, 2024 | Issued Comments |
Public Works disability access review Public Works · PW-DAC | Sep 23, 2024 | Oct 8, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 26, 2024 | Sep 26, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 27, 2024 | Sep 30, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 4, 2024 | Nov 13, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 4, 2024 | Nov 12, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 5, 2024 | Nov 5, 2024 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Dec 5, 2024 | Dec 5, 2024 | Approved |
Public Works disability access review Public Works · PW-DAC | Dec 5, 2024 | Dec 5, 2024 | Approved |
Zoning review Planning · CP-ZOC | Dec 5, 2024 | Dec 5, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 6, 2024 | Feb 11, 2025 | Administrative |
Addendum 1: Selective demolition
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 11, 2025 | Feb 27, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 5, 2025 | Mar 5, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Mar 6, 2025 | May 14, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 6, 2025 | Apr 9, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 6, 2025 | Mar 26, 2025 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Mar 6, 2025 | Mar 10, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 6, 2025 | In progress | Administrative |
Street use and mapping Public Works · DPW-BSM | Apr 22, 2025 | May 10, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 4, 2025 | In progress | In Progress |
Public Utilities Commission review Public Utilities · SFPUC | Nov 18, 2025 | Dec 2, 2025 | Approved |
Addendum 2: Foundation
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 18, 2025 | Jul 28, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 29, 2025 | Aug 5, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Aug 5, 2025 | Sep 17, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 5, 2025 | Sep 11, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Aug 5, 2025 | Aug 6, 2025 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Aug 5, 2025 | Aug 7, 2025 | Issued Comments |
Public Health HEALTH-MH | Aug 5, 2025 | Aug 8, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Aug 5, 2025 | In progress | — |
Street use and mapping Public Works · DPW-BSM | Sep 11, 2025 | Sep 11, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 20, 2025 | Nov 20, 2025 | Issued Comments |
Public Health HEALTH-MH | Dec 15, 2025 | Dec 15, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 24, 2026 | May 26, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 24, 2026 | Apr 29, 2026 | Issued Comments |
Public Health HEALTH-MH | Apr 24, 2026 | May 4, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 20, 2026 | Sep 11, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 20, 2026 | Aug 27, 2026 | Issued Comments |
Public Health HEALTH-MH | Aug 20, 2026 | Aug 24, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Public Health HEALTH-MH | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 3: Superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 8, 2025 | Aug 18, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 12, 2025 | Aug 18, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Aug 18, 2025 | May 5, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 18, 2025 | Oct 7, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 18, 2025 | Sep 11, 2025 | Administrative |
Street use and mapping Public Works · DPW-BSM | Aug 18, 2025 | Sep 17, 2025 | Not Applicable |
Permit Processing Center Building Inspection · PPC | Aug 18, 2025 | In progress | — |
Building plan review Building Inspection · BLDG | Apr 24, 2026 | Jun 3, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 24, 2026 | May 20, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 21, 2026 | Aug 24, 2026 | Approved |
Building plan review Building Inspection · BLDG | Aug 21, 2026 | Oct 8, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 21, 2026 | Sep 2, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 4: Arch, civil, mep & t-24
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 6, 2025 | Nov 17, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 17, 2025 | Nov 17, 2025 | Administrative |
Permit Processing Center Building Inspection · PPC | Nov 17, 2025 | In progress | In Progress |
Zoning review Planning · CP-ZOC | Nov 18, 2025 | In progress | — |
Building plan review Building Inspection · BLDG | Nov 18, 2025 | Dec 8, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 18, 2025 | Dec 4, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Nov 18, 2025 | Jan 13, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 18, 2025 | Dec 29, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 18, 2025 | Dec 11, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Nov 18, 2025 | Dec 19, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 18, 2025 | Dec 2, 2025 | Approved |
Public Health HEALTH-MH | Nov 18, 2025 | Nov 19, 2025 | Issued Comments |
Public Works disability access review Public Works · PW-DAC | Dec 15, 2025 | Jan 6, 2026 | Issued Comments |
Public Health HEALTH-MH | Dec 15, 2025 | Dec 15, 2025 | Approved |
Building plan review Building Inspection · BLDG | Apr 24, 2026 | May 1, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 24, 2026 | May 5, 2026 | Approved |
Electrical plan review Building Inspection · MECH-E | Apr 24, 2026 | May 7, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 24, 2026 | May 14, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 24, 2026 | May 20, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Apr 24, 2026 | Jun 5, 2026 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 24, 2026 | Apr 30, 2026 | Approved |
Public Works disability access review Public Works · PW-DAC | Apr 24, 2026 | May 7, 2026 | Approved |
Public Health HEALTH-MH | Apr 24, 2026 | May 4, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Oct 28, 2026 | Oct 28, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | — | In progress | — |
Electrical plan review Building Inspection · MECH-E | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Urban forestry Public Works · DPW-BUF | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $28,900,000
| Name | Role | License on permit |
|---|---|---|
| Jane Y Chan Dpw/Bureau Of Architecture | Architect | C28245 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026