1251 Dolores St
San Francisco permit 202203099567 · Mission
Interior remodel including kitchen and baths, new stairs,removal of portions of existing decks, new windows,new hvac & electrical as required.small extension off back side of house withing buildable area.
- Filed
- Mar 9, 2022
- Issued
- Mar 13, 2023 (12 months after filing)
- Completed
- Oct 21, 2024 (19 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 9 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Once
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 9, 2022 | Mar 11, 2022 | — |
Zoning review Planning · CP-ZOC | Mar 11, 2022 | Sep 14, 2022 | — |
Permit Processing Center Building Inspection · PPC | Mar 11, 2022 | Mar 10, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Jul 29, 2022 | Jul 29, 2022 | — |
Building plan review Building Inspection · BLDG | Sep 15, 2022 | Mar 9, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 15, 2022 | Oct 11, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Sep 15, 2022 | Sep 16, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 15, 2022 | Oct 3, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Mar 10, 2023 | Mar 13, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $400,000
| Name | Role | License on permit |
|---|---|---|
| Philip Christopher Rossington Rossington Architecture | Architect | C25251 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025