743 Carolina St
San Francisco permit 202203099600 · Potrero Hill
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to pa 202104269305: interior layout change; ground floor and basement popout in the rear yard, 2nd floor addition to the average depth of neighboring building
- Filed
- Mar 9, 2022
- Issued
- Mar 13, 2023 (12 months after filing)
- Completed
- Not completed yet
- Review stops
- 26 stops across 6 departments
- Comments issued
- Once, by Building Inspection
- Put on hold
- 4 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 10, 2022 | Mar 10, 2022 | — |
Zoning review Planning · CP-ZOC | Mar 10, 2022 | Sep 15, 2022 | — |
Planning neighborhood notice Planning · CP-NP | Jul 29, 2022 | Aug 2, 2022 | — |
Zoning review Planning · CP-ZOC | Nov 30, 2022 | Nov 30, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 1, 2022 | Jan 4, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 5, 2023 | Jan 11, 2023 | — |
Permit Center Permit Center · PERMIT-CTR | Jan 5, 2023 | Jan 12, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 6, 2023 | Jan 13, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jan 6, 2023 | Jan 6, 2023 | — |
Fire prevention review Fire Department · SFFD | Jan 6, 2023 | Jan 6, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jan 17, 2023 | Jan 17, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jan 17, 2023 | Mar 13, 2023 | — |
Addendum 1: Foundation/superstructure/arch/mep/final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 8, 2023 | May 19, 2023 | — |
Building plan review Building Inspection · BLDG | May 19, 2023 | Jul 27, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 19, 2023 | Jul 21, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 19, 2023 | May 24, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 19, 2023 | May 31, 2023 | — |
Permit Processing Center Building Inspection · PPC | May 19, 2023 | Sep 20, 2023 | Administrative |
Street use and mapping Public Works · DPW-BSM | Jul 20, 2023 | Aug 8, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 20, 2023 | Jul 26, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 21, 2023 | Sep 11, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 11, 2023 | Sep 11, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 11, 2023 | Sep 16, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 11, 2023 | Sep 14, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 18, 2023 | Sep 18, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 20, 2023 | Nov 27, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $100,000
| Name | Role | License on permit |
|---|---|---|
| Feifei Feng Moment X | Architect | C39268 |
| Michael Chan Michael Chan Engineering | Engineer | 72969 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025