2534 28th Av
San Francisco permit 202203109748 · Sunset/Parkside
New horizontal addition at rear. new veritical 3rd fl addition & decks. new exterior cladding throughout. modifications to front facade. reconfiguration of all interior walls. new interior stairs, relocate interior bathrooms, renovate existing kitchen.
- Filed
- Mar 10, 2022
- Issued
- May 14, 2025 (38 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 37 stops across 6 departments
- Comments issued
- 5 times, by Building Inspection, Fire Department, Public Works
- Put on hold
- Twice
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 10, 2022 | Mar 29, 2022 | — |
Zoning review Planning · CP-ZOC | Mar 29, 2022 | Jan 30, 2023 | — |
Permit Processing Center Building Inspection · PPC | Mar 29, 2022 | May 30, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Nov 3, 2022 | Jan 30, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 30, 2023 | Apr 5, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 30, 2023 | Feb 23, 2023 | — |
Fire prevention review Fire Department · SFFD | Jan 30, 2023 | Apr 7, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jan 30, 2023 | Feb 1, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 20, 2023 | Apr 27, 2023 | — |
Zoning review Planning · CP-ZOC | Apr 26, 2023 | May 15, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 26, 2023 | May 5, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Apr 26, 2023 | May 30, 2023 | — |
Fire prevention review Fire Department · SFFD | May 15, 2023 | May 15, 2023 | — |
Building plan review Building Inspection · BLDG | May 30, 2023 | May 30, 2023 | — |
Central Permit Bureau Building Inspection · CPB | May 30, 2023 | May 14, 2025 | Administrative |
Addendum 1: Final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 14, 2025 | May 27, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 28, 2025 | Jun 27, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jun 27, 2025 | Aug 26, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jun 27, 2025 | Aug 20, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 27, 2025 | Aug 19, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jun 27, 2025 | Jul 23, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 27, 2025 | Jul 8, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 27, 2025 | Jul 1, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jun 27, 2025 | Jul 14, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 27, 2025 | Jun 27, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 27, 2025 | Dec 29, 2025 | Administrative |
Mechanical plan review quality control Building Inspection · MECH-QC | Jul 23, 2025 | Jul 23, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 13, 2025 | Sep 19, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 29, 2025 | Nov 4, 2025 | Approved |
Building plan review Building Inspection · BLDG | Nov 5, 2025 | Nov 12, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 18, 2025 | Nov 18, 2025 | Approved |
Zoning review Planning · CP-ZOC | Dec 15, 2025 | Dec 16, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Dec 15, 2025 | Dec 15, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Dec 15, 2025 | Dec 17, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 15, 2025 | Dec 29, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 15, 2025 | Dec 17, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 29, 2025 | In progress | In Progress |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,041,831
| Name | Role | License on permit |
|---|---|---|
| Zachary Benjamin Meade Pristerro | Architect | C36088 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022