2534 28th Av

San Francisco permit 202203109748 · Sunset/Parkside

AdditionFull plan reviewIssued
Street view · Apr 2022
Google Street View of 2534 28th Av, Apr 2022
Scope of work
As written on the permit application.

New horizontal addition at rear. new veritical 3rd fl addition & decks. new exterior cladding throughout. modifications to front facade. reconfiguration of all interior walls. new interior stairs, relocate interior bathrooms, renovate existing kitchen.

Timeline
Key dates from the city record.
Filed
Mar 10, 2022
Issued
May 14, 2025 (38 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
37 stops across 6 departments
Comments issued
5 times, by Building Inspection, Fire Department, Public Works
Put on hold
Twice

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Mar 29, 2022—

Zoning review

Planning · CP-ZOC

Jan 30, 2023—

Permit Processing Center

Building Inspection · PPC

May 30, 2023—

Planning neighborhood notice

Planning · CP-NP

Jan 30, 2023—

Building plan review

Building Inspection · BLDG

Apr 5, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Feb 23, 2023—

Fire prevention review

Fire Department · SFFD

Apr 7, 2023—

Street use and mapping

Public Works · DPW-BSM

Feb 1, 2023—

Building plan review

Building Inspection · BLDG

Apr 27, 2023—

Zoning review

Planning · CP-ZOC

May 15, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

May 5, 2023—

Street use and mapping

Public Works · DPW-BSM

May 30, 2023—

Fire prevention review

Fire Department · SFFD

May 15, 2023—

Building plan review

Building Inspection · BLDG

May 30, 2023—

Central Permit Bureau

Building Inspection · CPB

May 14, 2025Administrative

Addendum 1: Final plans

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

May 27, 2025Approved

Central Permit Bureau

Building Inspection · CPB

Jun 27, 2025Administrative

Zoning review

Planning · CP-ZOC

Aug 26, 2025Approved

Building plan review

Building Inspection · BLDG

Aug 20, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Aug 19, 2025Administrative

Mechanical and energy plan review

Building Inspection · MECH

Jul 23, 2025Issued Comments

Fire prevention review

Fire Department · SFFD

Jul 8, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jul 1, 2025Issued Comments

Urban forestry

Public Works · DPW-BUF

Jul 14, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jun 27, 2025Approved

Permit Processing Center

Building Inspection · PPC

Dec 29, 2025Administrative

Mechanical plan review quality control

Building Inspection · MECH-QC

Jul 23, 2025Approved

Urban forestry

Public Works · DPW-BUF

Sep 19, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Nov 4, 2025Approved

Building plan review

Building Inspection · BLDG

Nov 12, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Nov 18, 2025Approved

Zoning review

Planning · CP-ZOC

Dec 16, 2025Approved

Fire prevention review

Fire Department · SFFD

Dec 15, 2025Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Dec 17, 2025Approved

Urban forestry

Public Works · DPW-BUF

Dec 29, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 17, 2025Approved

Central Permit Bureau

Building Inspection · CPB

In progressIn Progress

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$1,041,831
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Zachary Benjamin Meade

Pristerro

ArchitectC36088
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202203109748 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record