199 Moultrie St
San Francisco permit 202203159998 · Bernal Heights
Primary bedroom and bathroom horizontal addition on the top floor. roof deck under 500 sf.
- Filed
- Mar 15, 2022
- Issued
- Apr 28, 2023 (13 months after filing)
- Completed
- Mar 25, 2024 (11 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 22 stops across 4 departments
- Comments issued
- Once, by Public Utilities
- Put on hold
- 5 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 15, 2022 | Mar 17, 2022 | — |
Zoning review Planning · CP-ZOC | Mar 17, 2022 | Sep 22, 2022 | — |
Permit Processing Center Building Inspection · PPC | Mar 17, 2022 | Apr 3, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Jul 29, 2022 | Sep 12, 2022 | — |
Building plan review Building Inspection · BLDG | Sep 23, 2022 | Jan 4, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 23, 2022 | Oct 20, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Sep 23, 2022 | Sep 23, 2022 | — |
Building plan review Building Inspection · BLDG | Jan 4, 2023 | Jan 27, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 27, 2023 | Jan 31, 2023 | — |
Zoning review Planning · CP-ZOC | Feb 7, 2023 | Feb 8, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Feb 7, 2023 | Apr 3, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 7, 2023 | Feb 21, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Apr 3, 2023 | Apr 28, 2023 | — |
Addendum 1: Final - structural, mechanical , t-24
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 3, 2023 | May 3, 2023 | — |
Building plan review Building Inspection · BLDG | May 3, 2023 | Jul 10, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Jun 8, 2023 | Jun 8, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 14, 2023 | Jul 13, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jul 13, 2023 | Jul 14, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 17, 2023 | Jul 27, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 2, 2023 | Aug 2, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 4, 2023 | Aug 4, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 4, 2023 | Aug 9, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $150,000
| Name | Role | License on permit |
|---|---|---|
| Karen F Curtiss Red Dot Studio Architecture | Architect | C31453 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025