San Francisco permit 202203230622 · Mission

Seismic retrofit or foundationFull plan reviewApproved
Street view · Feb 2025
Google Street View of 3019 23rd St #0, Feb 2025
Scope of work
As written on the permit application.

Interior,exterior and soft story structural upgrade. rehab 6unit,3 story apt bldg.reconstrct (e)wood stairs,(e)wood siding&(e)window in-kind.(n)roof covering.repair or replacement all(e)fixtures, finishes and casework@all(e)kitchen&bathroom. replace space conditioning system.

Timeline
Key dates from the city record.
Filed
Mar 23, 2022
Issued
Not issued yet
Completed
Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
20 stops across 6 departments
Comments issued
None
Put on hold
3 times
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

May 9, 2022—

Zoning review

Planning · CP-ZOC

May 11, 2022—

Permit Processing Center

Building Inspection · PPC

Aug 22, 2023Administrative

Building plan review

Building Inspection · BLDG

May 22, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Jun 7, 2023—

Electrical plan review

Building Inspection · MECH-E

Mar 15, 2023—

Fire prevention review

Fire Department · SFFD

Jun 7, 2023—

Street use and mapping

Public Works · DPW-BSM

Sep 1, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Sep 7, 2022—

Disability access review

Mayor's Office on Disability · MOD

Aug 21, 2023Approved

Electrical plan review

Building Inspection · MECH-E

May 2, 2023—

Electrical plan review

Building Inspection · MECH-E

May 2, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Jun 8, 2023—

Fire prevention review

Fire Department · SFFD

Jun 7, 2023—

Electrical plan review

Building Inspection · MECH-E

Jun 13, 2023—

Street use and mapping

Public Works · DPW-BSM

Jun 14, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Jun 20, 2023—

Zoning review

Planning · CP-ZOC

Jun 27, 2023—

Central Permit Bureau

Building Inspection · CPB

In progressIn Progress

Building Inspection

417-86

In progress—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Approved
Estimated cost
$895,500
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Susan G Aitken

Hamilton & Aitken Arch.

ArchitectC17466
Ryan Bogart

Zpa Structural Engineers

Engineer6104
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202203230622 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record