61 Capp St #0
San Francisco permit 202203281031 · Mission
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to pa# 202203029095. update information - existing w.c. at ground floor. no change of plumbing unit count.
- Filed
- Mar 28, 2022
- Issued
- Mar 28, 2022 (within 1 month of filing)
- Completed
- Sep 23, 2022 (6 months after issuance)
- Review stops
- 6 stops across 3 departments
- Comments issued
- Not recorded for this permit
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Mar 28, 2022 | Mar 28, 2022 | — |
Intake Building Inspection · INTAKE | Mar 28, 2022 | Mar 28, 2022 | — |
Building plan review Building Inspection · BLDG | Mar 28, 2022 | Mar 28, 2022 | — |
Fire prevention review Fire Department · SFFD | Mar 28, 2022 | Mar 28, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 28, 2022 | Mar 28, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Mar 28, 2022 | Mar 28, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Tomer Maymon Tomer Maymon, Aia | Architect | C31492 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025